Lead-Time Monitor
Published lead times for eleven equipment classes compiled from OEM lead-time guides, Census M3 unfilled orders over shipments, ISM supplier deliveries and backlog disclosures in filings. Every cell carries its OEM and date.
50 weeksLV switchgear, published lead time, Schneider Electric Lead Times Guide, September 2026 edition. Public headline as of September 2, 2026.
- 50 weeks
- LV switchgear (LVDO A to F), made to order, Schneider Electric Lead Times Guide, September 2026, flagged extended vs August
- 5.67 months
- Unfilled orders over shipments, NAICS 3353 electrical equipment, Census M3, July 2026 (3.2 in 2017 to 2019)
- 171 days
- Capital expenditure lead time, ISM Manufacturing Report On Business, August 2026
- +91%
- PPI power and distribution transformers (WPU117409), July 2026 vs January 2020; switchgear (WPU1175) +78%
What it covers
Eleven equipment classes: large power transformers, medium power transformers, pad-mount distribution transformers, MV switchgear, LV switchgear and switchboards, MCC and busway, UPS, diesel gensets, chillers, CDUs, and drives and PLC CPUs. For each class: the OEM-published schedule where one exists, the OEM's own statement in filings or press, the third-party survey figure labelled as theirs, and the backlog disclosed in filings. Monthly, with the publication each figure came from.
- Cadence
- Monthly, first business day, after the Schneider guide (about the 2nd) and the M3 release
- Compiled from
- Schneider Electric monthly Lead Times Guide (124 product rows, September 2026 edition); Siemens LV schedules as republished; Census M3 NAICS 3353 unfilled orders and shipments; ISM Report On Business supplier deliveries and capex lead-time table; BLS PPI WPU117409 and WPU1175; 10-K, 10-Q and 8-K backlog for POWL, CAT, GEV, ETN, VRT, GNRC, CMI
- Delivered as
- Excel workbook, Web dashboard
- Updates
- Quarterly updates, one year included
- Onboarding
- Onboarding call
- Support
- Ad hoc analyst calls
- Tier
- Headline free; class detail Pro; history and API Institutional
Who uses it and what it decides
- Plant and facilities engineersWhether to release the switchgear PO now or wait, and which class gates the energization date.
- Datacenter developers and owner's repsThe month the site can energize, and the carrying cost of the longest-lead item on the list.
- Electrical contractors and distributorsWhat delivery to carry in a bid, and which OEM to steer a job to this quarter.
- Equity and credit analysts on industrialsWhether backlogs are lengthening or clearing, a month ahead of the earnings print.
Methodology
What the headline is
50 weeks is the made-to-order lead time Schneider Electric prints for its low-voltage switchgear families (LVDO A, B, C, D and F) in the September 2026 Lead Times Guide, published 2 September 2026, with each of those six rows flagged as extended against the August edition. It is the longest lead time any OEM publishes with a date on it. The rows are in 03-schneider-flags-sep-2026.csv beside the launch piece.
The headline is always the longest OEM-published figure, never a survey number. When Siemens, Eaton or ABB publish a longer dated schedule, the headline moves to it and says so.
What it is compiled from
Version 0.1 is public records only. No panel, no survey, no calls.
- OEM-published schedules. Schneider Electric Lead Times Guide, monthly, 124 product rows parsed to CSV (switchboards 18 to 34 weeks, LV switchgear 45 to 50, MV 15 to more than 40, MCC 6 to 27, busway 24 to 40, ATS 6 to 27, drives 4 to 32, September 2026). Siemens LV schedules as republished by VAWN (LV switchgear 54 weeks, switchboards 32 to 41, busduct 27, August 2026). Rockwell publishes no product-level figure; that cell reads “none published”.
- Backlog leg. Census M3 unfilled orders over monthly shipments for NAICS 3353 (Census code 35C): 5.67 months in July 2026 against about 3.2 in 2017 to 2019. Also turbines and generators (TGP), 7.35 months.
- Deliveries leg. ISM Manufacturing Report On Business: supplier deliveries index 59.3 and the capital expenditure lead time of 171 days, August 2026.
- Price leg. BLS PPI WPU117409 (transformers, 381.8 in July 2026) and WPU1175 (switchgear, 419.3), rebased to January 2020.
- Filings leg. Backlog in dollars from Powell 10-Q ($2.4B, $1.3B shipping within 12 months, June 30 2026), Caterpillar 10-Q ($72.1B, $29.2B beyond 12 months), GE Vernova 8-K, Eaton 8-K, Vertiv 8-K ($15.0B, December 2025, not disclosed since), Generac 8-K, and the Cummins Q4 2025 call (“orders well into 2028”).
- Third-party surveys, labelled as theirs. Wood Mackenzie (128 weeks power transformers, 144 GSU, 44 MV switchgear, Q2 2025; above 160 weeks in 2026) as reported by POWER and pv magazine; Terrapin Construction Group (June 2026); Origin Partners (May 2026). Where two disagree (gensets: Terrapin 50 to 110 weeks, Origin 26 to 40), both are printed as a conflict.
Every cell includes the document, the OEM and the date. Nothing is estimated where a published figure exists.
What is free and what is paid
- Free: the headline number, this page, the eleven-class range chart in Introducing the Open Factory Lead-Time Monitor, and the monthly index letter.
- Pro ($40 a month or $400 a year): every class and every source, monthly, with the Schneider edition-to-edition flags and the M3, ISM and PPI series.
- Institutional (quote): the workbook and dashboard, the full edition history (the Schneider history file starts with September 2026), the API, quarterly updates for a year, an onboarding call and ad hoc analyst calls.
Articles built on it
Transformer Lead Times Hit 143 Weeks, Why Your Switchgear Costs 50% More Than in 2021, Cummins and Caterpillar Are Sold Out Through 2028, Chillers Are the 60-Week Problem, Vertiv Stopped Reporting Its Backlog and One Steel Mill Gates Every US Transformer all draw their lead-time and backlog figures from this table. Charts read Source: Open Factory Lead-Time Monitor.
Version history
- 0.1 (September 2026). Eleven classes. Schneider September 2026 edition, M3 through July 2026, PPI through July 2026, ISM through August 2026, filings through Q2 2026. Public records only.
What version 1 adds
A distributor and EPC panel reporting quoted versus shipped lead time by OEM and class, so the Monitor shows what a buyer was told and what arrived. Panel size and response rate will print on this page only when they are true, per the methodology. Also planned: Eaton and ABB dated schedules if they publish them, and a chiller class fed by the OEM order releases Munters, Trane and Carrier already issue.
Known gaps
PLC CPUs have no published lead time from any OEM; the cell says so. Large power transformers have no OEM schedule. The class is carried on Wood Mackenzie’s survey and the Siemens Energy statement of “up to five years” (February 2024). STS and PDUs have no public series at all. The Schneider guide is the OEM’s planning document and says it is “not to be relied upon for actual orders”. We print it as published and say whose it is.
Questions
How is this different from reading the Schneider guide myself?
The guide is one OEM, one month, 124 rows, and it is replaced each month. The Monitor keeps every edition, puts eleven classes and every source side by side, and adds the Census, ISM and filings legs that no OEM publishes.
Are quoted and shipped lead times both tracked?
Version 0.1 is published (quoted) lead times only. Shipped versus quoted comes with the distributor and EPC panel in version 1.
Why is the headline LV switchgear and not transformers?
It is the longest class for which an OEM publishes a dated schedule. Transformer figures are third-party surveys (Wood Mackenzie, Terrapin) and are labelled as theirs, never headlined as ours.
What does 'flagged extended' mean?
Schneider colours a cell orange when the lead time is longer than the prior edition. We record the flag so the month-to-month direction is on the record.
Free calculators built on this model
Articles built on this model

Dry Cooler or Cooling Tower: What the Water Bill Says in 15 Markets
A thousand gallons of water and sewer costs $24.80 in Douglas County, Georgia and $8.68 in Baton Rouge as of October 2026, and since a 50 MW open cooling tower needs about 300 million gallons a year, Open Factory's MEP Cost Table puts the gap at $3.6 million a year.

Fiber Laser Cutters: What a $500,000 Price Gap Buys
A Chinese 6 to 12 kW fiber laser sells for $45,000 to $85,000 FOB in December 2025 and lands at about $128,000 after the 41% duty stack, while federal buyers paid $645,000 to $1.75 million in 2025, a $504,000 gap to the cheapest award Open Factory's Equipment Price Benchmark itemizes.

Tariffs, September 2026: The Actual Schedule for Machinery and Electrical Gear
As of September 2026 a 2,500 kVA pad-mount transformer pays 25% US duty from every origin and 50% from China, while a low-voltage panel with its PLC pays 0% from Mexico, 10% from Germany, 12.5% from Japan and 40.2% from China, per Open Factory's Tariff Exposure Calculator.

SendCutSend: How a Bootstrapped Reno Shop Became a $1 Billion Parts Factory
SendCutSend cuts an aluminum bracket in 2 to 4 production days with no minimum quantity, has shipped more than 30 million parts to 300,000 customers from three US plants, and raised $110 million at a $1.01 billion valuation in May 2026. Open Factory's Lead-Time Monitor tracks the turnaround.

Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line
A prefabricated electrical room for a 50 MW datacenter is not cheaper: Open Factory's Datacenter MEP Cost Table lands the skid route at $3.51M per MW against $3.47M stick-built, 1% more, but 27 weeks faster at 95 weeks from power-block PO to energization against 122, as of August 2026.

The Recommended Spares List Is Where the Margin Hides
On public awards Open Factory can read, the spares line is 0.8% of a transformer award, 2% of a genset and 20% of a breaker buy, and the City of Ocala paid $40,197.50 per ABB R-Mag breaker in November 2023 and $44,499.75 in November 2025 with no second quote.

800 VDC Will Strand Your White-Space Frame Agreement
NVIDIA set a ship date for 800 VDC on August 11, 2026, with the MGX power rack due in the second half of 2026. Open Factory finds a five-year 415 V UPS and AC busway frame agreement puts 40 to 60% of its dollars into superseded SKUs.

What 50 MW Costs in 15 US Markets
A 50 MW connection requested in Northern Virginia in 2026 energizes in 2033 after $75 million of collateral and a 14 year contract, while the same 50 MW in Houston posts no rule-mandated security and can be live in 2028, per Open Factory's Large-Load Cost Table as of August 2026.

Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin
Liquidated damages in public transformer, switchgear and genset contracts run about 0.5% of price a week, capped at 5%, so as of July 2026 a week of delay on a 50 MW datacenter hall costs about $2.7 million against $74,000 of LDs, per Open Factory's Large-Load Cost Table.

How to Write an RFQ for Capital Equipment in 2026
An equipment RFQ in 2026 has to settle escalators, LDs, milestones and tariff refunds: the City of Ocala agreed $8,070,340 for two 105 MVA autotransformers in August 2023 and approved $9,170,340 for the same units on April 28, 2026, a $1.1 million PPI escalator, per Open Factory's Bid-Tab Price Book.

The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT
Texas had about 474 GW of large-load interconnection requests as of August 2026, and ERCOT's March 26, 2026 status table shows 9.0 GW approved to energize and 5.8 GW energized, so about 2% has permission to draw power, as tracked in Open Factory's Large-Load Cost Table.

CloudNC and Limitless Labs: AI Is Coming for the CNC Programming Bottleneck
CloudNC and Limitless Labs raised $40 million between them from 16 June to 8 September 2026 to automate CNC programming for the 4,790 CNC tool programmers in America's 16,619 machine shops, and Open Factory's seat math shows a 50% CAM cut returns about $22,139 a year per programmer.

The R-454B Summer: What the Refrigerant Switch Did to Chiller Prices
A 20 lb cylinder of R-454B cost $345 in 2021 and $700 to $2,000 in July and August 2025, the switch raised Carrier chiller list prices 10% in March 2024 and March 2025, and Open Factory finds the 563 lb charge in a 500-ton chiller is 1.2% of the machine.

OFCI vs Design-Build: How Hyperscalers Buy Chillers and Colo Developers Do Not
Owner-furnished, contractor-installed chillers and CDUs for a 20 MW liquid-cooled hall cost $27.9 million against $32.8 million through the mechanical subcontract, a saving of $4.9 million or 14.9%, because OFCI strips a 15% subcontractor markup and 10% GC fee, per Open Factory's Datacenter MEP Cost Table as of June 2026.

Grainger's 2017 Confession: The Year a Distributor Admitted Its List Prices Were Fiction
On April 18, 2017, W.W. Grainger told investors its first quarter fell short because customers responded to across-the-board list price cuts and new web prices on about 450,000 SKUs, and US gross margin fell 1.7 points in one quarter, a reset Open Factory's Bid-Tab Price Book traces through 2026.

Reading a Switchgear Quote: The Eleven Line Items That Hide the Schedule
A medium-voltage switchgear quote has eleven line items and four of them move the delivery date more than the price. Riverside Public Utilities paid $2,561,551.88 for one 15 kV metal-clad lineup in June 2024 and it was still in the factory eighteen months later, per Open Factory's Bid-Tab Price Book.

1,250 Hours: Reading BMW's Humanoid Pilot as a Buyer
BMW's Figure 02 humanoid pilot delivered about 1,250 operating hours in ten months at Spartanburg in 2025, or 0.6 of one worker's year, moving more than 90,000 sheet-metal parts, and it is the only pilot with a disclosed runtime among the nine Open Factory's OEM Disclosure Scorecard scores.

The $306k Machine: A Record Half-Year With Fewer Units
US manufacturers ordered a record $3.44 billion of metalworking machinery in the first half of 2026 on 11,243 machines, 2.6% fewer than in the second half of 2025, so the average order rose to about $306,000 from $277,000, as tracked in Open Factory's Bid-Tab Price Book.

From 36 Weeks to Stock: The ControlLogix Lead-Time Cycle
Rockwell's own bulletin listed a ControlLogix 5580 controller at 35 calendar days on September 22, 2021 and 208 days on October 26, 2022, and Open Factory's Lead-Time Monitor, which holds eleven editions of that bulletin, now reads the PLC line at stock.

A Factory Owner's Guide to the PJM Capacity Charge
PJM's RTO capacity clearing price rose from $28.92 to $329.17 per MW-day in two auctions, so a 5 MW plant in Met-Ed territory pays about $568,000 for capacity in the delivery year starting June 1, 2026 against about $50,000 in 2024, per Open Factory's PJM Capacity Charge Estimator.

A Robot Costs $61k. The Cell Costs $150k
North American buyers paid $61,198 per robot arm in 2025, but a working cell costs 1.9 to 2.4 times that, $113,336 to $144,432 for three common cobot cells priced line by line in Open Factory's Bid-Tab Price Book as of September 2026.

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One slot for a 384 MW GE Vernova 7HA.02 turbine takes a $60 million reservation payment, 20% of a $300 million machine. GE Vernova ended June 2026 with 116 GW under contract, 63 GW as slot reservations, and $25.8 billion paid in advance, which Open Factory's MEP Cost Table carries.

Who Gets the IEEPA Refund
The IEEPA refund goes to the importer of record, not the buyer who paid a surcharge, and CBP puts the pool at about $166 billion across 53 million entries and 330,000 importers as of March 2026. Open Factory's Tariff Exposure Calculator flags the refundable lines on every 2025 entry.

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects and about 2 GW of it runs, or 2.2%, while EIA's July 2026 inventory lists 68.1 GW of planned gas nationwide. Open Factory's Lead-Time Monitor forecasts what energizes by the end of 2028.

Compressed Air Is 10% of Your Factory's Power Bill
Compressed air takes about 10% of a typical plant's electricity by DOE's count, and a 200 hp rotary screw compressor running 6,000 hours a year at the 2025 US industrial rate of 8.62 cents per kWh costs about $70,000 a year. Open Factory finds a leak program worth $83,000.

Five Majors Bought Their Way Into Liquid Cooling. Here Is the Price List
Five majors paid $16.3 billion of disclosed prices for liquid cooling companies in seventeen months, with Ecolab buying CoolIT for $4.75 billion at 29 times EBITDA on March 20, 2026 and Eaton closing Boyd Thermal at $9.5 billion and 22.5 times, per Open Factory's deal table.

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant over five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines at 85% utilization and $3.78/MMBtu, with first power in 17, 27 and 30 months, per Open Factory's MEP Cost Table in 2026.

Nox Metals: The Detroit Startup Cutting Aluminum Plate in 36 Hours
Nox Metals quotes saw-cut aluminum plate instantly and delivers in an average of 36 hours, against the 3 to 5 days a typical service center takes to quote, after an $11.5 million seed on 14 June 2026, and Open Factory's Lead-Time Monitor lists cut plate as its first raw material.

The 2 MW Plant Service Upgrade Nobody Budgets Right
A 400-person plant adding 2 MW of service pays $400k to $1.2M for the items the switchgear quote omits, and with the utility-owned pad-mount at 52 to 104 weeks the crane lands in week 74. Open Factory's Large-Load Cost Table shows the sequencing that pulls energization forward by 20 weeks.

Chillers Are the 60-Week Problem
A water-cooled chiller over 1,000 tons quotes at 50 to 70 weeks in the United States as of May 22, 2026, an air-cooled machine over 500 tons at 40 to 60 weeks, and Census M3 puts HVAC unfilled orders at $18.6 billion in July 2026, per Open Factory's Lead-Time Monitor.

What 2,439 Public Change Orders Show About Electrical and Mechanical Contractors
Across 1,096 federal electrical and mechanical construction contracts awarded in fiscal years 2019 to 2024, with 2,439 priced change orders, the median contract closed 1.8% above its award price and the dollars closed 9.5% above it. Open Factory's Public Bid-Tab Price Book holds the full dataset.

Copper at $6.77: How a 50% Tariff Shows Up in a 200-Amp Panel
COMEX copper set a record $6.77 per pound on August 7, 2026, and Open Factory's panel math shows a 200-amp residential service that carried $270 of copper at 2024 prices now carries $440, about $30 of it the tariff expectation priced into COMEX.

The Used and Refurbished Market Nobody Indexes
Fifteen vendors bid $41,200 to $101,253 on one 2,500 kVA pad-mount transformer for Fayetteville's public utility in September 2025, a 2.5x spread at 10 to 35 week lead times, and a dealer shipping from stock lists it at $104,000, 1.77x the median bid, per Open Factory's Bid-Tab Price Book.

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Between July 2025 and August 2026, 1872, Foundational Industries and Hadrian raised $1.41 billion to build autonomous American factories: $15 million, $25 million and $1.37 billion respectively, with Hadrian's four plants totalling just under 3 million square feet. Open Factory's Lead-Time Monitor will track each one's delivered lead time.

Who Bought the EV Plants' Machines
Companies cancelled, closed or downsized 61 US clean-energy projects worth $34.8 billion in 2025, but most was never built, and the EV plant machines that did reach the secondary market sold at 3% to 37% of reference value in the court records Open Factory read.

When a Megapack Beats a Static UPS
A 24 MW, 48 MWh block of twelve Tesla Megapack 2 XL units costs about $14.4 million installed at January 2026 prices, $10.1 million after the 30% storage credit, against about $17.5 million for the N+1 static UPS in a 20 MW hall, per Open Factory's Datacenter MEP Cost Table.

The OEM Disclosure Scorecard: Who Tells Buyers Anything
Open Factory's OEM Disclosure Scorecard version 0.1 finds that the eighteen largest electrical, power and cooling OEMs publish only 12 of 90 cells a buyer needs, with 16 Partials and 62 Noes: GE Vernova alone scores 2 of 5, ten score 1 and seven score 0, as of September 2026.

Rockwell's 250 Basis Points: How Tariffs Show Up in Your PLC Quote
Tariffs are 100 basis points of a Rockwell Automation bill in fiscal 2026, inside the 250 basis points of total price the company guided on its August 4, 2026 call, and Open Factory's Bid-Tab Price Book tracks the pass-through against the 150 basis points of underlying price.

What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract
Microsoft pays about $112 per MWh for 835 MW from the Crane nuclear restart on a 20-year contract, a 70 to 90% premium to wholesale, so Open Factory's Large-Load Cost Table treats that as the reference price for a 15-year factory power contract as of December 2025.

Datacenter Construction Is Eating Your Electricians
Loudoun County electrical contractor payrolls rose 138% from 5,615 people in 2019 to 14,022 in March 2026, while the national BLS median electrician wage rose 12.5% against 25.6% CPI from May 2019 to May 2025, per Open Factory's Large-Load Cost Table.

Why Your Switchgear Costs 50% More Than in 2021
The BLS producer price index for switchgear stood at 394.8 in July 2026, 78% above January 2021, and medium-voltage switchgear is up 50% since 2021 per Wood Mackenzie. Open Factory's decomposition finds inputs explain 36 of the 78 points and margin the other 43.

The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power
Since July 4, 2025, the 30% federal investment credit survives only for fuel cells among gas-fired on-site power, with wind and solar needing construction by July 4, 2026 and gas CHP getting nothing, and Open Factory's math turns a 2.5-year payback at $210/MWh in California into 1.7 years.

Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate
Open Factory estimates Vertiv's unpublished order backlog at $16 to $20 billion at June 30, 2026, central case about $17.4 billion, up from the last reported $15.0 billion at December 31, 2025, with current deferred revenue doubling from $1.81 billion to $3.63 billion in six months.

Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First
A generator step-up transformer ordered in the United States was quoted at 143 weeks in the second quarter of 2025, a substation power transformer at 128 weeks and medium-voltage switchgear at 44, per Wood Mackenzie, against about 50 weeks in 2021, and Open Factory's Lead-Time Monitor lists both readings.

Quote Check: What Your Switchgear Quote Should Have Said
Open Factory's Quote Check tool places a switchgear quote against public awards: Riverside Public Utilities paid $2,254,387.50 for a 15 kV metal-clad lineup in May 2025, 52% above the $1,481,321 median of 12 public awards dated December 2016 to May 2025 in the Public Bid-Tab Price Book.

One Steel Mill Gates Every US Transformer
Every pound of domestic grain-oriented electrical steel in a US transformer core is melted at Cleveland-Cliffs Butler Works, a plant with a 920 mm maximum coil width, and the transformer PPI is up 91% since December 2019 at 381.8 in July 2026, per Open Factory's Lead-Time Monitor.

MES Is a Consulting Product
The Bureau of Engraving and Printing has paid $110.1 million for MES support services since May 2021 against $4.64 million of Oracle licences in FY2025, about five dollars of consulting per dollar of software, the pattern Open Factory found across 44 public MES and SCADA awards as of October 2025.

Tariff Bill of Materials: What Sections 232 and 301 Add to a UPS, a Lineup, a Genset and a Megapack
A 1 MW UPS assembled in the United States carries about 17 points of duty and the same UPS imported from China carries 55, under the tariff stack in force on October 10, 2025. The 50% copper tariff is 3.8 of those 17 points, per Open Factory's Tariff Exposure Calculator.

The Copper and Wire Price Sheet, Weekly
Open Factory's Copper and Wire Price Sheet, refreshed every Monday, prices a foot of 500 kcmil copper at $9.48 of metal at the IMF's $6.14 a pound for July 2026, or $9.70 at that month's $6.28 COMEX open, with a price per foot for 13 conductor sizes.

Introducing the Large-Load Cost Table: 15 Markets Side by Side
Open Factory's Large-Load Cost Table, version 0.1, compares a 50 MW connection across 15 US utilities on eight tariff cells each: 53 of the 120 cells come from primary documents, 20 from trade press, 2 from arithmetic, and 45 are not published anywhere, as of August 2026.

The $2,850 Report That Says Nothing
IBISWorld's $2,850 ProcurementIQ switchgear report prices the whole category at one $37,300 benchmark, while the 118 public awards in Open Factory's Public Bid-Tab Price Book run from $12,492 for a pad-mount switch in 2019 to $3,827,000 for a 34.5 kV lineup in September 2024.

Introducing the Public Bid-Tab Price Book
Open Factory's Public Bid-Tab Price Book launches as version 0.1 with 2,712 public award lines and 51 price bands, and across 297 lines dated January 2024 to August 2026 the median three-phase pad-mount price runs from $153 per kVA at 75 to 167 kVA to $30 at 1,500 to 2,500.

Cummins and Caterpillar Are Sold Out Through 2028
Cummins is taking generator orders well into 2028 and Caterpillar closed June 2026 with $72.1 billion of firm backlog, and Open Factory's Lead-Time Monitor shows published lead times of 50 to 66 weeks for a 1,500 to 2,000 kW diesel genset and 90 to 110 weeks above 3,500 kW.

The 171-Day Capex Lead Time: ISM's Most Ignored Table
The average US manufacturing buyer commits to capital equipment 171 days ahead of need in the August 2026 ISM report, with 27% committing more than a year out, against 147 days in December 2019. Open Factory's Lead-Time Monitor rebuilds the series back to 2007.

Book-to-Bill League Table, Q2 2026: Every Electrical OEM
Powell Industries posted a book-to-bill of 3.0 in the quarter to June 30 2026, booking $934 million of switchgear orders against $312 million shipped, and all eight electrical OEMs that print a ratio sit above 1.0, down to Eaton at 1.2, in Open Factory's Book-to-Bill League Table.

Introducing the Open Factory Lead-Time Monitor
Schneider Electric quotes low-voltage switchgear at 50 weeks from release to manufacturing in its September 2026 Lead Times Guide, and Open Factory's Lead-Time Monitor, launched as version 0.1, puts all eleven equipment classes in one table, of which only four have an OEM-published lead time.