ModelVersion 0.1Compiling data
Lead-Time Monitor
Published lead times for eleven equipment classes compiled from OEM lead-time guides, Census M3 unfilled orders over shipments, ISM supplier deliveries and backlog disclosures in filings. Every cell carries its OEM and date.
50 weeksLV switchgear, published lead time, Schneider Electric Lead Times Guide, September 2026 edition. Public headline as of September 2, 2026.
- 50 weeks
- LV switchgear (LVDO A to F), made to order, Schneider Electric Lead Times Guide, September 2026, flagged extended vs August
- 5.67 months
- Unfilled orders over shipments, NAICS 3353 electrical equipment, Census M3, July 2026 (3.2 in 2017 to 2019)
- 171 days
- Capital expenditure lead time, ISM Manufacturing Report On Business, August 2026
- +91%
- PPI power and distribution transformers (WPU117409), July 2026 vs January 2020; switchgear (WPU1175) +78%
What it covers
Eleven equipment classes: large power transformers, medium power transformers, pad-mount distribution transformers, MV switchgear, LV switchgear and switchboards, MCC and busway, UPS, diesel gensets, chillers, CDUs, and drives and PLC CPUs. For each class: the OEM-published schedule where one exists, the OEM's own statement in filings or press, the third-party survey figure labelled as theirs, and the backlog disclosed in filings. Monthly, with the publication each figure came from.
- Cadence
- Monthly, first business day, after the Schneider guide (about the 2nd) and the M3 release
- Compiled from
- Schneider Electric monthly Lead Times Guide (124 product rows, September 2026 edition); Siemens LV schedules as republished; Census M3 NAICS 3353 unfilled orders and shipments; ISM Report On Business supplier deliveries and capex lead-time table; BLS PPI WPU117409 and WPU1175; 10-K, 10-Q and 8-K backlog for POWL, CAT, GEV, ETN, VRT, GNRC, CMI
- Delivered as
- Excel workbook, Web dashboard
- Updates
- Quarterly updates, one year included
- Onboarding
- Onboarding call
- Support
- Ad hoc analyst calls
- Tier
- Headline free; class detail Pro; history and API Institutional
Who uses it and what it decides
- Plant and facilities engineersWhether to release the switchgear PO now or wait, and which class gates the energization date.
- Datacenter developers and owner's repsThe month the site can energize, and the carrying cost of the longest-lead item on the list.
- Electrical contractors and distributorsWhat delivery to carry in a bid, and which OEM to steer a job to this quarter.
- Equity and credit analysts on industrialsWhether backlogs are lengthening or clearing, a month ahead of the earnings print.
Methodology
What the headline is
50 weeks is the made-to-order lead time Schneider Electric prints for its low-voltage switchgear families (LVDO A, B, C, D and F) in the September 2026 Lead Times Guide, published 2 September 2026, with each of those six rows flagged as extended against the August edition. It is the longest lead time any OEM publishes with a date on it. The rows are in 03-schneider-flags-sep-2026.csv beside the launch piece.
The headline is always the longest OEM-published figure, never a survey number. When Siemens, Eaton or ABB publish a longer dated schedule, the headline moves to it and says so.
What it is compiled from
Version 0.1 is public records only. No panel, no survey, no calls.
- OEM-published schedules. Schneider Electric Lead Times Guide, monthly, 124 product rows parsed to CSV (switchboards 18 to 34 weeks, LV switchgear 45 to 50, MV 15 to more than 40, MCC 6 to 27, busway 24 to 40, ATS 6 to 27, drives 4 to 32, September 2026). Siemens LV schedules as republished by VAWN (LV switchgear 54 weeks, switchboards 32 to 41, busduct 27, August 2026). Rockwell publishes no product-level figure; that cell reads “none published”.
- Backlog leg. Census M3 unfilled orders over monthly shipments for NAICS 3353 (Census code 35C): 5.67 months in July 2026 against about 3.2 in 2017 to 2019. Also turbines and generators (TGP), 7.35 months.
- Deliveries leg. ISM Manufacturing Report On Business: supplier deliveries index 59.3 and the capital expenditure lead time of 171 days, August 2026.
- Price leg. BLS PPI WPU117409 (transformers, 381.8 in July 2026) and WPU1175 (switchgear, 419.3), rebased to January 2020.
- Filings leg. Backlog in dollars from Powell 10-Q ($2.4B, $1.3B shipping within 12 months, June 30 2026), Caterpillar 10-Q ($72.1B, $29.2B beyond 12 months), GE Vernova 8-K, Eaton 8-K, Vertiv 8-K ($15.0B, December 2025, not disclosed since), Generac 8-K, and the Cummins Q4 2025 call (“orders well into 2028”).
- Third-party surveys, labelled as theirs. Wood Mackenzie (128 weeks power transformers, 144 GSU, 44 MV switchgear, Q2 2025; above 160 weeks in 2026) as reported by POWER and pv magazine; Terrapin Construction Group (June 2026); Origin Partners (May 2026). Where two disagree (gensets: Terrapin 50 to 110 weeks, Origin 26 to 40), both are printed as a conflict.
Every cell includes the document, the OEM and the date. Nothing is estimated where a published figure exists.
What is free and what is paid
- Free: the headline number, this page, the eleven-class range chart in Introducing the Open Factory Lead-Time Monitor, and the monthly index letter.
- Pro ($40 a month or $400 a year): every class and every source, monthly, with the Schneider edition-to-edition flags and the M3, ISM and PPI series.
- Institutional (quote): the workbook and dashboard, the full edition history (the Schneider history file starts with September 2026), the API, quarterly updates for a year, an onboarding call and ad hoc analyst calls.
Articles built on it
Transformer Lead Times Hit 143 Weeks, Why Your Switchgear Costs 50% More Than in 2021, Cummins and Caterpillar Are Sold Out Through 2028, Chillers Are the 60-Week Problem, Vertiv Stopped Reporting Its Backlog and One Steel Mill Gates Every US Transformer all draw their lead-time and backlog figures from this table. Charts read Source: Open Factory Lead-Time Monitor.
Version history
- 0.1 (September 2026). Eleven classes. Schneider September 2026 edition, M3 through July 2026, PPI through July 2026, ISM through August 2026, filings through Q2 2026. Public records only.
What version 1 adds
A distributor and EPC panel reporting quoted versus shipped lead time by OEM and class, so the Monitor shows what a buyer was told and what arrived. Panel size and response rate will print on this page only when they are true, per the methodology. Also planned: Eaton and ABB dated schedules if they publish them, and a chiller class fed by the OEM order releases Munters, Trane and Carrier already issue.
Known gaps
PLC CPUs have no published lead time from any OEM; the cell says so. Large power transformers have no OEM schedule. The class is carried on Wood Mackenzie’s survey and the Siemens Energy statement of “up to five years” (February 2024). STS and PDUs have no public series at all. The Schneider guide is the OEM’s planning document and says it is “not to be relied upon for actual orders”. We print it as published and say whose it is.
Questions
How is this different from reading the Schneider guide myself?
The guide is one OEM, one month, 124 rows, and it is replaced each month. The Monitor keeps every edition, puts eleven classes and every source side by side, and adds the Census, ISM and filings legs that no OEM publishes.
Are quoted and shipped lead times both tracked?
Version 0.1 is published (quoted) lead times only. Shipped versus quoted comes with the distributor and EPC panel in version 1.
Why is the headline LV switchgear and not transformers?
It is the longest class for which an OEM publishes a dated schedule. Transformer figures are third-party surveys (Wood Mackenzie, Terrapin) and are labelled as theirs, never headlined as ours.
What does 'flagged extended' mean?
Schneider colours a cell orange when the lead time is longer than the prior edition. We record the flag so the month-to-month direction is on the record.
Free calculators built on this model
Articles built on this model

Tariffs, September 2026: The Actual Schedule for Machinery and Electrical Gear
A 2,500 kVA pad-mount transformer entered at Long Beach on September 9, 2026 pays 25% duty whether it was built in Monterrey, Osaka or Mumbai, and 50% if it was built in Jiangsu. A low-voltage panel with the PLC already in it pays 0% from Mexico, 10% from…

SendCutSend: How a Bootstrapped Reno Shop Became a $1 Billion Parts Factory
SendCutSend has shipped more than 30 million laser-cut parts to more than 300,000 customers from three plants in Reno, Nevada, Paris, Kentucky and Arlington, Texas, and until May 2026 it did so on a $750,000 laser financed by its founder, bank loans and…

Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line
Austin Energy paid Crown Texas $725,183 for one prefabricated 16 by 60 foot control house in June 2023. The house was $489,270 of that. The truck was $12,500, the stairs shipped separately for $5,000, and the crew that unloaded and anchored it billed…

The Recommended Spares List Is Where the Margin Hides
The City of Ocala bought 15 ABB R-Mag breakers in November 2023 at $40,197.50 each, four more in November 2025 at $44,499.75 each, and it had no second quote either time because WESCO is ABB's sole distributor for public power in peninsular Florida. That is…

800 VDC Will Strand Your White-Space Frame Agreement
NVIDIA put a ship date on 800 VDC on August 11, 2026: the MGX power rack arrives in the second half of 2026. A 2 MW-per-row power center with an 800 VDC busway follows in 2027, and a DC power block that converts grid power in one step is the design for new…

What 50 MW Costs in 15 US Markets
A 50 MW connection requested in Northern Virginia this quarter energizes in 2033, after posting $75 million of collateral and signing for 14 years. The same 50 MW in Houston posts no rule-mandated security, signs no minimum-take contract, and can be live in…

Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin
A week of delay on a 50 MW datacenter hall costs about $2.7 million. The liquidated damages clause in the transformer contract behind that hall pays back $74,000 for the same week, and stops paying after ten weeks. On a 2 MW plant the ratio is worse:…

How to Write an RFQ for Capital Equipment in 2026
The City of Ocala, Florida agreed to pay $8,070,340 for two 105 MVA autotransformers in August 2023 and approved $9,170,340 for the same two units on April 28, 2026, seven months before the first one arrives. The $1.1 million difference is one clause: a PPI…

The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT
Governor Abbott's August 3, 2026 letter to the PUCT and ERCOT put the number at "approximately 474 gigawatts of requests to connect to the Texas grid," more than five times ERCOT's 85,508 MW peak record, about 90% of it data centers. ERCOT's own status table…

CloudNC and Limitless Labs: AI Is Coming for the CNC Programming Bottleneck
CloudNC and Limitless Labs raised $40 million between them in the twelve weeks from 16 June to 8 September 2026, and both are aiming it at the same 4,790 people. That is how many CNC tool programmers work in America's machine shops in the last industry-level…

The R-454B Summer: What the Refrigerant Switch Did to Chiller Prices
A 20 lb cylinder of R-454B cost $345 in 2021 and traded at $700 to $2,000 in July and August 2025. On May 26, 2026 EPA finalised a rule (91 FR 31284, effective July 27) that lets the last R-410A houses be installed and leaves every comfort-cooling chiller on…

OFCI vs Design-Build: How Hyperscalers Buy Chillers and Colo Developers Do Not
A water-cooled chiller over 1,000 tons quoted at 50 to 70 weeks in May 2026. The developer who lets the mechanical subcontractor buy it after the guaranteed maximum price pays about 15% more for a machine that arrives 20 weeks late. The route the…

Grainger's 2017 Confession: The Year a Distributor Admitted Its List Prices Were Fiction
On April 18, 2017, W.W. Grainger told investors that the first quarter "clearly fell short of our expectations, driven primarily by the stronger than anticipated customer response to our U.S. strategic pricing actions." It had cut list prices across the…

Reading a Switchgear Quote: The Eleven Line Items That Hide the Schedule
Riverside Public Utilities paid $2,561,551.88 for one 15 kV metal-clad switchgear lineup in June 2024, and the unit was still in the factory eighteen months later. The board memo that approved the purchase put delivery in the first quarter of 2026; the next…

1,250 Hours: Reading BMW's Humanoid Pilot as a Buyer
BMW's humanoid pilot, the most documented one on earth, delivered about 1,250 operating hours in ten months, which is 0.6 of one worker's year. Hold that number against the next vendor video. Figure 02 moved more than 90,000 sheet-metal parts at Spartanburg…

The $306k Machine: A Record Half-Year With Fewer Units
US manufacturers ordered $3.44 billion of metalworking machinery in the first half of 2026, the largest half-year since AMT's USMTO series began in 1998, and they did it on 11,243 machines, 2.6% fewer than in the second half of 2025. Divide one by the other…

From 36 Weeks to Stock: The ControlLogix Lead-Time Cycle
On September 22, 2021, Rockwell Automation's own lead-time bulletin listed a ControlLogix 5580 controller at 35 calendar days against a standard lead time of "Stock". On October 26, 2022, the same bulletin listed the same controller at 208 days, just under…

A Factory Owner's Guide to the PJM Capacity Charge
A 5 MW plant in Met-Ed territory will pay about $568,000 for capacity in the PJM delivery year that starts June 1, 2026. In the year that started June 1, 2024 the same plant, with the same load, paid about $50,000. Nothing on the plant floor changed. The RTO…

A Robot Costs $61k. The Cell Costs $150k
North American buyers ordered 36,766 robots for $2.25 billion in 2025, which is $61,198 per arm, and not one of those arms did anything on its own. A working cell, the arm plus the gripper, the guarding, the vision, the integrator's hours and the training,…

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One GE Vernova 7HA.02 is 384 MW. At the ~$790/kW that BNP Paribas estimates GE Vernova is now getting for a heavy-duty turbine (July 2026), that one machine is ~$300 million of equipment, and the 20% reservation payment that holds a production slot for it is…

Who Gets the IEEPA Refund
Ford told analysts this morning that it booked a $1.3 billion one-time benefit for IEEPA tariffs it paid between March 2025 and February 2026 (Ford Q1 2026 call, April 29, 2026). A plant that bought a German switchgear lineup last November and paid a 15%…

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects, and about 2 GW of it runs, which is 2.2%. Another 1.2% is under construction, 36% holds an air permit, and 60% exists as a press release. The same month…

Compressed Air Is 10% of Your Factory's Power Bill
A 200 hp rotary screw compressor running 6,000 hours a year at the 2025 US industrial rate of 8.62 cents per kWh costs about $70,000 a year in electricity, and over ten years it costs about $1.0M, of which $700,000 is the power bill. The DOE's own tip sheet…

Five Majors Bought Their Way Into Liquid Cooling. Here Is the Price List
Ecolab agreed on March 20 to pay $4.75 billion for CoolIT Systems, 29 times the next twelve months' adjusted EBITDA on about $550 million of CDU and cold-plate sales. Eight days earlier Eaton had closed its $9.5 billion purchase of Boyd Thermal, agreed in…

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant run for five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines. That is at 85% utilization with gas delivered at $3.78/MMBtu, and the ranking holds at every gas…

Nox Metals: The Detroit Startup Cutting Aluminum Plate in 36 Hours
Nox Metals quotes a saw-cut aluminum block in seconds and, by its lead investor's count, delivers it in an average of 36 hours, in a trade where the quote alone has taken three to five days. The company is fourteen months old. It launched out of Y…

The 2 MW Plant Service Upgrade Nobody Budgets Right
A 400-person plant adding 2 MW of service pays for five things the switchgear quote never mentions, and together they run $400k to $1.2M with one month of bridge power. The calendar is worse than the money: run the project the way most plants run it, utility…

Chillers Are the 60-Week Problem
A water-cooled chiller over 1,000 tons quotes at 50 to 70 weeks in the United States as of May 22, 2026. An air-cooled machine over 500 tons is 40 to 60 weeks and a coolant distribution unit 30 to 50. None of those is the longest line on a datacenter…

What 2,439 Public Change Orders Show About Electrical and Mechanical Contractors
The median electrical or mechanical contract in our set of 1,096 federal awards closed 1.8% above its award price. The dollars closed 9.5% above it. That gap between the typical contract and the typical dollar is the whole story of change orders: most jobs…

Copper at $6.77: How a 50% Tariff Shows Up in a 200-Amp Panel
COMEX copper settled at a record $6.77 per pound on August 7, 2026, the day after the Democratic Republic of Congo banned concentrate exports. The 50% Section 232 copper tariff has been in force since August 1, 2025, and it does not apply to the cathode that…

The Used and Refurbished Market Nobody Indexes
Fifteen vendors bid on the same 2,500 kVA pad-mount transformer for Fayetteville's public utility in September 2025 and the unit prices ran from $41,200 to $101,253, a 2.5x spread on one spec sheet, with quoted lead times from 10 to 35 weeks. The dealer that…

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Three companies are building the autonomous American factory from three directions, and between July 2025 and August 2026 they raised $1.41 billion to do it. 1872 took $15 million to run robotic steel fabrication out of a 1903 building in Cincinnati.…

Who Bought the EV Plants' Machines
Companies cancelled, closed or downsized $34.8 billion of US clean-energy projects in 2025, 61 of them, against $12.3 billion of new announcements, and EV and battery plants were more than $21 billion each of the loss. That is E2's count, and it is the wrong…

When a Megapack Beats a Static UPS
A 24 MW, 48 MWh block of twelve Tesla Megapack 2 XL units costs about $14.4 million installed at January 2026 prices, $10.1 million after the 30% storage credit, and the N+1 static UPS it would sit next to in a 20 MW hall costs about $17.5 million. A grid…

The OEM Disclosure Scorecard: Who Tells Buyers Anything
Twelve of ninety cells. That is how many times one of the eighteen largest electrical, power and cooling OEMs selling into US factories and datacenters publishes, in a form a buyer can open without an account, one of five things a buyer needs: a dated lead…

Rockwell's 250 Basis Points: How Tariffs Show Up in Your PLC Quote
"For the full year, we still expect about 250 basis points of price realization, with about one hundred basis points from tariff-related pricing and about 150 basis points from underlying price." That is Rockwell Automation's CFO, Christian Rothe, in the…

What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract
Microsoft is paying about $112 per MWh for 835 MW from a reactor that shut in 2019, and it signed for 20 years. That is the Jefferies estimate for the Crane restart, published five days after the deal, and Bloomberg Intelligence put it at $100 (Bloomberg,…

Datacenter Construction Is Eating Your Electricians
Loudoun County's electrical contractors had 5,615 people on payroll in 2019. In the fourth quarter of 2025 they had 13,352, and by March 2026 14,022, a 138% increase in six years. That is what a few gigawatts of datacenter construction does to one trade in…

Why Your Switchgear Costs 50% More Than in 2021
The BLS producer price index for switchgear and switchboard manufacturing stood at 394.8 in July 2026, 78% above January 2021. Wood Mackenzie's survey puts medium-voltage switchgear at +50% since 2021 and circuit breakers at +47%, as reported by POWER…

The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power
On July 4, 2025, Congress cut the federal investment credit for every kind of on-site generation a factory can buy except one. Wind and solar lose it unless construction starts by July 4, 2026. Gas engines and turbines never had it. Natural-gas fuel cells,…

Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate
Vertiv's order backlog was $15.0 billion on December 31, 2025, up 109% in a year, on a fourth-quarter book-to-bill of ~2.9x. That was the last time the company printed the number. The April 22 and July 29, 2026 releases have no backlog, no orders and no…

Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First
A generator step-up transformer ordered in the United States in the second quarter of 2025 was quoted at 143 weeks on average, per Wood Mackenzie's T&D supply chain survey published October 15, 2025. A substation power transformer was quoted at 128 weeks and…

Quote Check: What Your Switchgear Quote Should Have Said
Riverside Public Utilities paid $2,254,387.50 for one 15 kV metal-clad switchgear lineup in May 2025. The median public award for a 5 to 15 kV metal-clad lineup in the Open Factory Public Bid-Tab Price Book is $1,481,321 across 12 awards from five utilities…

One Steel Mill Gates Every US Transformer
Every pound of domestic grain-oriented electrical steel in a US transformer core is melted in one electric arc furnace in Butler, Pennsylvania, at a plant with 0.3 million net tons of configured raw steel capacity and a maximum finished coil width of 920 mm.…

MES Is a Consulting Product
The Bureau of Engraving and Printing has paid Deloitte $110.1 million since May 2021 for "Manufacturing Execution System (MES) support services" at its two currency plants. The Oracle licences the system runs on cost $4.64 million this year. Five dollars of…

Tariff Bill of Materials: What Sections 232 and 301 Add to a UPS, a Lineup, a Genset and a Megapack
A 1 MW UPS assembled in the United States from the parts a US OEM actually buys carries about 17 points of federal duty in its ex-works price. The same UPS imported finished from China carries 55. The "50% copper tariff" that every quote now cites is 3.8 of…

The Copper and Wire Price Sheet, Weekly
A foot of 500 kcmil copper holds $9.48 of metal at the $6.14 a pound the IMF recorded for July 2026. The distributor who sells it priced it off a COMEX open of $6.28 that month, so the same foot was $9.70 before insulation, margin or freight. The Copper and…

Introducing the Large-Load Cost Table: 15 Markets Side by Side
Fifteen utilities, eight tariff cells each, and 45 of the 120 cells have no published number. That is the honest headline of the Open Factory Large-Load Cost Table, which launches as version 0.1: for a 50 MW connection in fifteen US markets, the study fee,…

The $2,850 Report That Says Nothing
IBISWorld's ProcurementIQ profile for "Switchgear Systems in the US" prices the whole category at one benchmark, $37,300 per system. The 118 public switchgear awards in the Public Bid-Tab Price Book run from $12,492 for a two-way S&C pad-mount switch…

Introducing the Public Bid-Tab Price Book
On March 19, 2024, Fayetteville Public Works Commission in North Carolina opened twelve bids for four 2,500 kVA three-phase pad-mount transformers and the unit prices ran from $64,285 to $219,000, a 3.4x spread on one stock number, with quoted lead times…

Cummins and Caterpillar Are Sold Out Through 2028
Cummins is taking generator orders "well into 2028" and Caterpillar closed June 2026 with $72.1 billion of firm backlog, $29.2 billion of it not shipping inside twelve months. Those two sentences come from Cummins' fourth-quarter call on February 5, 2026 and…

The 171-Day Capex Lead Time: ISM's Most Ignored Table
The average manufacturing buyer now commits to capital equipment 171 days ahead of need, and 27% of them commit more than a year out. Those two numbers sit in the Buying Policy table on the last page of the ISM Manufacturing Report On Business, below the…

Book-to-Bill League Table, Q2 2026: Every Electrical OEM
Powell Industries booked $934 million of switchgear orders in the quarter to June 30 2026 and shipped $312 million, a book-to-bill of 3.0. That is the top of the table. The bottom of the table is Eaton at 1.2, and Eaton is the only one of eight…

Introducing the Open Factory Lead-Time Monitor
A low-voltage switchgear section ordered from Schneider Electric today is quoted at 50 weeks from release to manufacturing, per the September 2026 edition of Schneider's Lead Times Guide, published September 2. That number is one of exactly four equipment…