Record
Every call we have made, with the date it can be checked.
A research desk earns trust by being scored, not by being cited. This page lists each forward-looking call in our articles and roadmaps as a one-line claim, the public series that settles it, and the date it resolves. On that date the row is marked right, partial or wrong with a note, and the original wording is never changed. 60 calls so far; 0 have come due. The next resolves October 31, 2026.
| Made | Call | Resolves | Scored against | Result |
|---|---|---|---|---|
Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate | Vertiv's Q3 2026 10-Q will print September 30, 2026 current deferred revenue of about $3.3B (low), $3.9B (mid) or $4.8B (high). Measured as: Vertiv ContractWithCustomerLiabilityCurrent at 2026-09-30, $ billion | Vertiv Q3 2026 10-Q via SEC XBRL, | Open | |
The 171-Day Capex Lead Time: ISM's Most Ignored Table | The transformer PPI (WPU117409) year-over-year rate keeps rising through about November 2026. Measured as: BLS PPI WPU117409 (transformers), year-over-year % change, monthly prints through Nov 2026 | BLS PPI series WPU117409 | Open | |
Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running | 3.0 GW of behind-the-meter datacenter generation is operating in the US at the end of 2026. Measured as: Operating US behind-the-meter datacenter generation capacity, GW, at end-2026 (Cleanview count) | Cleanview behind-the-meter datacenter report | Open | |
Book-to-Bill League Table, Q2 2026: Every Electrical OEM | ABB Electrification raises list prices on LV and MV gear in the second half of 2026. Measured as: ABB Electrification list price increases announced or reported for LV and MV products in H2 2026 | ABB Q3 and Q4 2026 results releases and distributor price-increase notices | Open | |
The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT | About 90 to 110 GW of the roughly 200 GW of ERCOT Batch Zero data center load under the Abbott audit survives verification. Measured as: GW of Batch Zero large-load requests surviving the PUCT/ERCOT verification audit | PUCT verification report (December 10, 2026) and December 17 open meeting; ERCOT Large Load Interconnection status reports | Open | |
The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power | Bloom Energy does not cut fuel-cell pricing in 2026. Measured as: Bloom Energy product pricing and gross margin trend, FY2026 | Bloom Energy FY2026 10-K and quarterly releases | Open | |
Why Your Switchgear Costs 50% More Than in 2021 | Switchgear producer prices will not fall before 2027 even if copper does; nothing that could reverse the rise is scheduled before 2027. Measured as: BLS switchgear and switchboard PPI (PCU335313335313), level vs 394.8 in Jul 2026 | FRED PCU335313335313, | Open | |
The 171-Day Capex Lead Time: ISM's Most Ignored Table | The switchgear PPI (WPU1175) year-over-year rate turns back up around February 2027 after sliding from 13.4% to 9.3%. Measured as: BLS PPI WPU1175 (switchgear), year-over-year % change, around Feb 2027 vs the preceding months | BLS PPI series WPU1175 | Open | |
Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate | Vertiv's FY2026 10-K will print a December 31, 2026 backlog between $16.4B and $26.2B, mid case $20.6B. Measured as: Vertiv backlog at 2026-12-31 as disclosed in the FY2026 10-K, $ billion | Vertiv FY2026 Form 10-K, SEC EDGAR CIK 0001674101 | Open | |
Who Gets the IEEPA Refund | A buyer whose PO carries the refund-allocation clause (seller files CAPE and remits) has its 2025 IEEPA duty back by early 2027. Measured as: Timing of CBP CAPE refund disbursement on 2025 entries and vendor remittance to buyers | CBP CSMS messages on CAPE refund issuance; Treasury Monthly Treasury Statement customs refunds | Open | |
The $306k Machine: A Record Half-Year With Fewer Units | A standard Japanese five-axis machining center ordered in September 2026 ships around April 2027 at the industry's current throughput. Measured as: Delivery month for a standard Japanese five-axis VMC ordered Sep 2026 (JMTBA backlog-to-sales months; builder quoted lead times) | JMTBA monthly order backlog and sales releases; DMG MORI IR backlog disclosures; Open Factory Equipment Price Benchmark delivery-date rows | Open | |
Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First | Generator step-up transformers are the class that eases first; cancelled renewable projects release 34.5 kV to 138 kV GSU delivery positions over the two years to late 2027. Measured as: Wood Mackenzie survey GSU lead time, weeks (143 in Q2 2025), relative to power and distribution classes | Wood Mackenzie T&D survey, | Open | |
1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory | A buyer of rack enclosures in 2027 will have a US-built option from Foundational Industries, whose first plant opens by the end of 2026. Measured as: Foundational Industries first US facility operational by end-2026 and shipping rack enclosures to customers in 2027 | Foundational Industries announcements and trade press | Open | |
Factory Automation Roadmap | Cobots pass 30% of North American robot units on a full-year basis in 2027. Measured as: A3 cobot share of North American robot units ordered, full-year 2027, percent | A3 annual North American robot orders release; The Robot Report coverage | Open | |
Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running | 7.4 GW of behind-the-meter datacenter generation is operating in the US at the end of 2027. Measured as: Operating US behind-the-meter datacenter generation capacity, GW, at end-2027 (Cleanview count) | Cleanview behind-the-meter datacenter report | Open | |
One Steel Mill Gates Every US Transformer | Cleveland-Cliffs' Butler Works cannot produce GOES coil wider than 920 mm before 2028 at the earliest. Measured as: Maximum finished GOES coil width at Butler Works; any wider mill or new US GOES line commissioned before 2028 | Cleveland-Cliffs 10-K and press releases, DOE award announcements | Open | |
Chillers Are the 60-Week Problem | Trane and Carrier have open 2027 chiller capacity; Modine and Munters do not. Measured as: Availability of 2027 chiller delivery slots at Trane and Carrier versus Modine (Airedale) and Munters, per filings, calls and published delivery windows | Trane, Carrier, Modine and Munters 2026 and 2027 earnings releases and order announcements (SEC EDGAR, Cision) | Open | |
Five Majors Bought Their Way Into Liquid Cooling. Here Is the Price List | CoolIT CDU hardware holds price through the 2026 to 2027 negotiation cycle; Ecolab moves margin into attached fluid, filtration and monitoring contracts instead of cutting hardware price. Measured as: CoolIT/Ecolab CDU hardware price per kW, 2026 to 2027 | Open Factory Equipment Price Benchmark CDU cell; Ecolab Global High-Tech segment pricing commentary in 10-K/10-Q | Open | |
Cooling Roadmap | Large water-cooled chiller lead times stay above 40 weeks through 2027. Measured as: Quoted lead time for water-cooled chillers over 1,000 tons, weeks, through Q4 2027 | Origin Partners equipment lead-times tracker; Open Factory Lead-Time Monitor | Open | |
Cooling Roadmap | CDU lead times fall in 2027, before chiller lead times do. Measured as: Quoted CDU lead time, weeks, in 2027 vs the 30 to 50 week May 2026 baseline | Origin Partners equipment lead-times tracker; Open Factory Lead-Time Monitor | Open | |
Cummins and Caterpillar Are Sold Out Through 2028 | Cummins and Caterpillar large-genset lead times do not shorten before 2028. Measured as: Published lead time for 1,500 kW and larger diesel gensets, weeks (Lead-Time Monitor genset rows) | Open Factory Lead-Time Monitor genset rows; Terrapin Construction Group lead-time sheet; Cummins and Caterpillar 10-Q backlog disclosures | Open | |
OFCI vs Design-Build: How Hyperscalers Buy Chillers and Colo Developers Do Not | The 50 to 70 week lead-time range for water-cooled chillers over 1,000 tons does not close before 2028. Measured as: Published lead time for water-cooled chillers over 1,000 tons, weeks (Lead-Time Monitor cell, currently Origin Partners tracker) | Origin Partners equipment lead-times tracker and successor editions; Open Factory Lead-Time Monitor chiller row | Open | |
Tariffs, September 2026: The Actual Schedule for Machinery and Electrical Gear | The Section 232 Annex III 15% tier will not be extended for machine tools past December 31, 2027; machining centers revert to MFN plus 25% on January 1, 2028. Measured as: Whether a proclamation extends heading 9903.82.10 (Annex III) for 8457.10.00 beyond 2027-12-31 | Federal Register proclamations amending Proclamation 11021 cl. 7; HTS chapter 99; CBP CSMS 68855869 | Open | |
Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First | US transformer lead times will not return to their 2019 level (about 50 weeks, under a year) before 2028. Measured as: Wood Mackenzie T&D survey average US power transformer lead time, weeks (128 in Q2 2025) | Wood Mackenzie T&D supply chain survey notes, | Open | |
Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate | Vertiv's 2027 output is allocated before 2027 starts: a PO for Vertiv power or thermal gear placed after December 2026 is a 2028 delivery unless it displaces another slot. Measured as: Quoted delivery dates on Vertiv UPS, busway, PDU and CDU orders placed in Q1 2027 | Vertiv FY2026 10-K backlog and shipment-window language; Lead-Time Monitor published UPS and CDU lead times (Terrapin, | Open | |
Cummins and Caterpillar Are Sold Out Through 2028 | A 3 MW diesel genset PO placed in September 2026 delivers between Q4 2027 and Q3 2028. Measured as: Delivery date of a 2,500 to 3,500 kW diesel genset ordered September 2026 (62 to 82 week lead time) | Open Factory Lead-Time Monitor genset rows; Terrapin Construction Group slot-reservation lead times; Central States Diesel Generators (https://csdieselgenerators.com/the-ai-data-center-boom-and-generator-shortage-lead-times-prices/) | Open | |
Factory Automation Roadmap | The next PLC lead-time spike comes with the 2027 to 2028 datacenter electrical build. Measured as: Rockwell ControlLogix / PLC lead time (distributor-reported), weeks, vs 2026 baseline | Rockwell supply-chain lead-times page; distributor lead-time reports; Open Factory Lead-Time Monitor PLC cell | Open | |
Factory Automation Roadmap | By 2028 the controller vendors sell the PLC as a subscription tied to their software stack. Measured as: Rockwell or Siemens offering PLC hardware under a subscription tied to its software stack (yes/no) by end-2028 | Rockwell Automation and Siemens Digital Industries product announcements, price lists and annual reports | Open | |
Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running | 15 GW of behind-the-meter datacenter generation is operating at the end of 2028 (base case), within a 10 to 22 GW range. Measured as: Operating US behind-the-meter datacenter generation capacity, GW, at end-2028 (Cleanview count); base 15 GW, range 10 to 22 GW | Cleanview behind-the-meter datacenter report | Open | |
Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running | Project Kilby, Homer City, GW Ranch and the back half of Project Matador do not reach their announced capacity until 2029 to 2031, not 2028. Measured as: Operating capacity at Kilby (Pecos, TX), Homer City (PA), GW Ranch (Pecos County, TX) and Fermi's Matador second phase at end-2028 versus announced capacity | EIA-860M planned and operating generator inventory, Chevron, Fermi America and Amazon filings and releases | Open | |
Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running | The twelve named campuses with 30.2 GW announced have 8.8 to 14.2 GW running by the end of 2028, with GW Ranch at zero. Measured as: Combined operating GW at end-2028 across the twelve named campuses (Frontier, VoltaGrid Oracle sites, Joule, Matador, Abilene, Monarch, Wartsila orders, Kilby, Homer City, Jupiter, Cheyenne, GW Ranch) | Cleanview behind-the-meter datacenter report, state air permits and company filings | Open | |
Chillers Are the 60-Week Problem | A buyer negotiating Trane applied chillers in H2 2026 gets 2028 delivery on standard terms and 2027 delivery only on OFCI terms with a slot fee. Measured as: Trane applied chiller delivery dates quoted for orders placed in H2 2026 on standard terms versus OFCI slot-fee terms | Trane Technologies earnings calls and backlog disclosures; Origin Partners equipment lead-time tracker | Open | |
Cooling Roadmap | By 2028 the CDU is bundled with switchgear and UPS in hyperscale reference designs and the standalone CDU quote disappears for hyperscale. Measured as: Presence of CDU in Vertiv/Schneider/Eaton hyperscale reference designs as a bundled line by 2028 (yes/no) | Vertiv, Schneider Electric and Eaton reference design documentation; NVIDIA partner reference architectures | Open | |
Cooling Roadmap | Large water-cooled chiller lead times fall toward 30 weeks in 2028. Measured as: Quoted lead time for water-cooled chillers over 1,000 tons, weeks, during 2028 | Origin Partners equipment lead-times tracker; Trane, Carrier, JCI published lead times; Open Factory Lead-Time Monitor | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | White-space distribution bought for under 200 kW per rack in 2026 is replaced or bypassed before full depreciation at any site hosting a 2027 or 2028 GPU generation. Measured as: Retrofit or bypass of sub-200 kW/rack busway and PDU at sites deploying 2027 to 2028 GPU racks | Hyperscaler and colo retrofit disclosures; Vertiv, Schneider, Eaton 800 VDC white-space product rollouts | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | BESS displaces the static UPS in new hyperscale halls that accept two nines of uptime by 2028. Measured as: Hyperscale new-build halls specifying utility-scale BESS in place of static UPS, by end-2028 (yes/no) | Hyperscaler design disclosures; Tesla Megapack deployment reports; Open Factory BESS-as-UPS coverage | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | Solid-state transformers appear at the 800 VDC boundary inside the datacenter hall from 2028. Measured as: Commercial SST deployments at the 800 VDC boundary inside a datacenter hall, from 2028 (yes/no) | Eaton (Resilient Power), ABB, Hitachi Energy, Heron Power product releases and customer announcements; LVDC SST working group | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | Large power transformer lead times do not fall below 100 weeks before 2029. Measured as: Large power transformer lead time, weeks, each year through 2028 | Wood Mackenzie transformer survey as reported by pv magazine; Open Factory Lead-Time Monitor | Open | |
What 50 MW Costs in 15 US Markets | Three markets (Houston under CenterPoint, Phoenix under SRP, northern Indiana under I&M) can still energize a 50 MW load requested in Q3 2026 in 2028. Measured as: Whether sub-threshold 50 MW loads requested in Q3 2026 take service in 2028 in CenterPoint, SRP and I&M territories | CenterPoint, SRP and Indiana Michigan Power large-load energization disclosures and earnings calls | Open | |
800 VDC Will Strand Your White-Space Frame Agreement | MV switchgear, transformers and gensets stay the same SKU under 800 VDC through 2029; UPS, busway and PDU SKUs change before then. Measured as: Whether published 800 VDC reference architectures (NVIDIA, Vertiv, Schneider) replace MV switchgear, transformer or genset SKUs, and whether they replace 415 V UPS, AC busway and AC PDU SKUs, by end-2029 | NVIDIA 800 VDC architecture blog and Vertiv 800 VDC releases | Open | |
Cooling Roadmap | Single-phase cold plates carry every GPU generation through 2029. Measured as: Primary cooling method of each NVIDIA (and peer) GPU rack generation released through 2029 | NVIDIA reference designs; Dell'Oro liquid cooling reports | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2028 to 2029 in Houston (CenterPoint), Phoenix under SRP, Salt Lake City (Rocky Mountain Power) and northern Indiana (I&M). Measured as: Energization year for a 50 MW request filed Q3 2026 in CenterPoint, SRP, Rocky Mountain Power and I&M territories | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2029 in Dallas (Oncor), AEP Texas, Phoenix under APS and Louisiana (Entergy). Measured as: Energization year for a 50 MW request filed Q3 2026 in Oncor, AEP Texas, APS and Entergy Louisiana territories | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Large-Load Policy Tracker by State | Dallas and Houston large loads energize in 2028 to 2029, assuming Batch Zero proceeds in 2027 with a smaller queue. Measured as: Energization year for Batch Zero large loads in Dallas and Houston (ERCOT) | ERCOT Batch Zero final transmission plan (fall 2027) and large-load updates; Open Factory Large-Load Cost Table | Open | |
What 50 MW Costs in 15 US Markets | A 50 MW load requested in Houston (CenterPoint) in Q3 2026 can be live in 2028 (table range 2028 to 2029). Measured as: Energization year for a sub-75 MW CenterPoint facility-extension load requested in Q3 2026 | CenterPoint Energy earnings disclosures on data center energizations (e.g.; ERCOT large-load reports | Open | |
Factory Automation Roadmap | A humanoid stays a pilot line item, not a capex line, through 2030; no public deck shows a RaaS rate under $20 an hour at two shifts. Measured as: Public humanoid RaaS rate per hour at two shifts, and any fleet deployment booked as capex, through 2030 | Agility, Figure, Apptronik public decks and filings; BMW and other operator pilot disclosures; Interact Analysis humanoid installations | Open | |
Cooling Roadmap | Two-phase and immersion cooling stay under 10% of liquid-cooled capacity through 2030. Measured as: Two-phase plus immersion share of liquid-cooled datacenter capacity, percent, each year to 2030 | Dell'Oro data center liquid cooling market reports; Uptime Institute cooling survey | Open | |
The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT | About 20 to 30 GW of the audited ERCOT Batch Zero data center load is drawing power by 2030. Measured as: ERCOT observed energized large-load (data center) capacity from the Batch Zero pool, GW, end of 2030 | ERCOT Large Load Interconnection Requests status table, observed energized row | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2029 to 2030 in the Carolinas (Duke) and Colorado (Xcel). Measured as: Energization year for a 50 MW request filed Q3 2026 in Duke Carolinas and Xcel Colorado territories | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2031 in Atlanta (Georgia Power) and Chicago (ComEd). Measured as: Energization year for a 50 MW request filed Q3 2026 in Georgia Power and ComEd territories | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | BESS does not displace the static UPS in plants with process loads (semiconductor, pharma, paper) through 2032. Measured as: Static UPS still specified for process-load plants (semiconductor, pharma, paper) through 2032 | Semiconductor, pharma and paper plant electrical specifications; UPS vendor segment disclosures (Vertiv, Schneider, Eaton) | Open | |
Datacenter Electrical Roadmap 2026 to 2032 | Solid-state transformers do not replace the oil-filled substation transformer at the fence through 2032; it stays the longest-lead item on the site. Measured as: Oil-filled substation transformer still specified at the fence and still the longest-lead site item, through 2032 | Wood Mackenzie transformer lead-time surveys; Heron Power and OEM MV SST deployments; Open Factory Lead-Time Monitor | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2031 to 2032 in the Bay Area (PG&E). Measured as: Energization year for a 50 MW request filed Q3 2026 in PG&E territory | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract | By 2032 hyperscalers will have 5.8 GW of nuclear under contract, 5.6 GW from already-built reactors, covering 6% to 9% of forecast datacenter load. Measured as: GW of hyperscaler nuclear PPAs in delivery in 2032; share from existing or restarted reactors; ratio to published US datacenter load forecasts | Constellation, Talen, Vistra, NextEra SEC filings; Kairos and Amazon SMR releases; LBNL, Grid Strategies and BloombergNEF datacenter load forecasts | Open | |
What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract | No reactor beyond those already named (Crane, Susquehanna, Clinton, Comanche Peak, Duane Arnold, plus the SMR agreements) will hold a hyperscaler contract delivering in 2032. Measured as: List of US reactors under hyperscaler PPA delivering in 2032 versus the December 2025 deal book (data/deal-book.csv) | SEC 8-K filings and press releases from Constellation, Talen, Vistra, NextEra, PSEG, Dominion and other nuclear owners announcing hyperscaler PPAs | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2031 to 2033 in Columbus (AEP Ohio). Measured as: Energization year for a 50 MW request filed Q3 2026 in AEP Ohio territory | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Introducing the Large-Load Cost Table: 15 Markets Side by Side | A 50 MW large-load request filed in Q3 2026 energizes in 2033 in Northern Virginia (Dominion). Measured as: Energization year for a 50 MW request filed Q3 2026 in Dominion territory | Utility energization dates for 50 MW requests filed in Q3 2026 (utility large-load reports and PUC dockets); Open Factory Large-Load Cost Table energization column (/models/large-load-cost-table/) | Open | |
Large-Load Policy Tracker by State | A 50 MW load applying in Columbus (AEP Ohio DCT) energizes in 2031 to 2033. Measured as: Energization year for a new 50 MW large-load connection in AEP Ohio territory | AEP Ohio data center tariff study tranche outcomes; Open Factory Large-Load Cost Table | Open | |
Large-Load Policy Tracker by State | A 50 MW load in Dominion territory (Northern Virginia) under GS-5 energizes in 2033. Measured as: Energization year for a new 50 MW large-load connection in Dominion Virginia territory | Virginia SCC dockets (PUR-2025-00058, PUR-2026-00056); Dominion large-load interconnection disclosures; Open Factory Large-Load Cost Table | Open | |
What 50 MW Costs in 15 US Markets | A 50 MW connection requested in Northern Virginia (Dominion GS-5) in Q3 2026 energizes in 2033. Measured as: Energization year for a 50 MW Dominion GS-5 load requested in Q3 2026 | Dominion Energy large-load queue disclosures; Virginia SCC dockets PUR-2025-00058 and PUR-2026-00056; JLL Global Data Center Outlook | Open |
How a call is scored
A call goes on this page when an article or roadmap states, in our own voice, that a measurable thing will happen by a date. Reported third-party forecasts do not count. On the resolve date we check the named source and mark the row right (the number and the direction), partial (direction right, number off, or the window slipped by a quarter), or wrong, with a one-line note. A call we no longer stand behind is marked withdrawn with the date and the reason, and stays on the page. The exact sentence each row was taken from is in the row's tooltip, and the piece is linked, so the wording can be checked against the original.
Disagree with a score, or see a call we missed? Write to [email protected] with the row's id.