ModelVersion 0.1Compiling data
Large-Load Cost Table
What a 50 MW connection costs and takes in 15 US markets: study fees, security per MW, minimum bills, contract terms, exit fees and realistic energization year, from tariffs and dockets.
2033realistic energization year for a new 50 MW load in Northern Virginia, Dominion Energy, from a 2026 application. Public headline as of August 21, 2026.
- $75M
- Collateral for 50 MW under Dominion Schedule GS-5 at $1.5 million per MW, LBNL and Brattle brief, August 10 2026
- 14 years
- Dominion GS-5 minimum term including a four-year ramp; AEP Ohio DCT up to 12; Georgia Power up to 15
- 85%
- Minimum bill as a share of contract demand, Dominion GS-5 (distribution and transmission) and AEP Ohio DCT cap
- 15
- Markets side by side, each cell linked to the tariff sheet, PUC order or ISO document it came from
What it covers
Fifteen US markets for a 50 MW connection: Northern Virginia (Dominion), Columbus (AEP Ohio), Atlanta (Georgia Power), Dallas-Fort Worth (Oncor), Houston (CenterPoint), West and South Texas (AEP Texas), the Carolinas (Duke), Phoenix (APS and SRP), Salt Lake City (Rocky Mountain Power), Louisiana (Entergy), Colorado (Xcel), Chicago (ComEd), the Bay Area (PG&E) and Northern Indiana (I&M). For each: MW threshold, whether the rule applies at 50 MW, study fee, security or collateral in dollars, minimum bill, contract term, ramp, exit fee, CIAC exposure and the realistic energization year with its basis.
- Cadence
- Updated as dockets move; reviewed monthly; energization years revisited each quarter
- Compiled from
- Utility tariff sheets and PUC orders (Virginia SCC PUR-2025-00058 and PUR-2026-00056, PUCO 24-508-EL-ATA, Georgia PSC docket 55378, PUCT Projects 58480 and 58481, Oregon PUC Order 26-154, CPUC D.25-07-039); ERCOT large-load status decks; PJM BRA results; the LBNL and Brattle large-load rate-design brief (August 2026); EIA industrial rates by state; JLL Global Data Center Outlook 2026 for time to power
- Delivered as
- Excel workbook, Web dashboard
- Updates
- Quarterly updates, one year included
- Onboarding
- Onboarding call
- Support
- Ad hoc analyst calls
- Tier
- Table free; history Pro; alerts Institutional
Who uses it and what it decides
- Datacenter developers and site selectorsWhich market energizes first, what the deposit per MW is, and how much cash a portfolio has locked in security.
- Factory owners adding 20 to 100 MWWhich regime a plant expansion lands in (below Texas's 75 MW, above AEP Ohio's 25 MW, inside Georgia's 100 MW rule) and what that costs.
- Lenders and investorsMinimum-bill and exit-fee exposure over a 12 to 15 year term, market by market.
Methodology
What the headline is
2033 is the year a 50 MW load applying to Dominion Energy Virginia in 2026 can realistically expect to energize. The basis is JLL’s Global Data Center Outlook 2026 (p.18), which puts Northern Virginia at about seven years to power for a new 50 MW site, and Dominion’s own load pipeline of about 70 GW against a 24.6 GW system peak as reported by Utility Dive in February 2026. The shortest markets in the table (Houston, Northern Indiana, Salt Lake City) are 2028 to 2029. The full column with its basis is in energization-years.csv.
The headline is the longest realistic energization year among the 15 markets. It moves when a utility publishes a schedule that changes it.
What it is compiled from
Version 0.1 is tariffs, orders and ISO documents. No developer interviews yet.
- Virginia. Dominion Schedule GS-5 approved 25 November 2025 (PUR-2025-00058): 25 MW threshold, 14-year term with a four-year ramp, 85% minimum for distribution and transmission and 60% for generation, $1.5 million per MW collateral. Mandatory CIAC for direct-connect transmission ordered 31 July 2026 (PUR-2026-00056 final order). Terms as summarised in the LBNL and Brattle brief, pp.4 to 7.
- Ohio. AEP Ohio Schedule DCT, approved 9 July 2025: $50,000 study fee for 50 to 100 MW, 85% minimum, ramp plus eight years, 36-month exit fee, collateral of 50% of term minimum charges. 17,861 MW under contract at February 2026 against an 8,000 to 10,500 MW peak. Tariff page.
- Georgia. PSC rule of 23 January 2025: 100 MW and above, contracts up to 15 years, upstream cost recovery.
- Texas. SB6 (signed 20 June 2025, 75 MW threshold); PUCT proposed 16 TAC 25.194 (12 March 2026): $50,000 per MW security plus $50,000 per MW fee; ERCOT Batch Zero approved 18 June 2026 with 438 GW tracked; the Governor’s 3 August 2026 audit directive at 474 GW.
- Oregon, Colorado, Indiana, Carolinas, California. PUC Order 26-154 (PGE Schedule 96, 10 to 30 years); Xcel’s April 2026 filing; I&M’s Cause 46097 settlement; Duke’s HLF proposal; CPUC D.25-07-039 and PG&E Rule 30.
- Capacity and rates. PJM BRA clearing prices from the 2028/29 results report; EIA Table 5.6.A industrial rates (Texas 6.58 cents per kWh, Virginia 9.31, Ohio 9.89, June 2026).
Every cell prints its verification status: VERIFIED against the primary document, or SECONDARY with the outlet named.
What is free and what is paid
- Free: the 15-market table as published in What 50 MW Costs in 15 US Markets, this page, and the Large-Load Interconnection Cost calculator with default inputs.
- Pro: the table’s history as dockets move, the 20 MW and 100 MW scale factors, and the minimum-bill cash schedules by market.
- Institutional: the workbook and dashboard, docket alerts when a cell changes, custom markets, quarterly updates for a year, an onboarding call and ad hoc calls.
Articles built on it
What 50 MW Costs in 15 US Markets, The 2 MW Plant Service Upgrade Nobody Budgets Right, A Factory Owner’s Guide to the PJM Capacity Charge and Datacenter Construction Is Eating Your Electricians. The rule calendar lives on the Large-Load Policy Tracker.
Version history
- 0.1 (August 2026). Fifteen markets. Tariffs and orders through 20 August 2026 (PUCT good-cause exception for ERCOT). Study fees and exit-fee amounts not published for Dominion; cells say so.
What version 1 adds
Developer interviews on actual study outcomes and actual energization dates against the tariff’s promise, and the utility’s study-queue position where a utility publishes one. Interview counts print here only when true.
Known gaps
Dominion’s study fee and exit-fee amounts were not in the sources opened. CenterPoint and ComEd security figures are implied averages from company statements (about $64,000 and $250,000 per MW), not tariff sheets, and are marked as such. Texas’s $50,000 per MW security is a proposed rule and does not apply at 50 MW. The table carries the 75 MW case beside it.
Questions
Why 50 MW?
It is the size most new tariffs are written around (median threshold 25 MW across 55 tariffs in the LBNL and Brattle brief) and it sits under Texas's 75 MW line, which makes the regimes comparable. Scale factors for 20 and 100 MW are in the Pro table.
How is the energization year chosen?
From the utility's or ISO's own statements where they exist (ERCOT Batch Zero dates, CenterPoint's 2029 plan, AEP Ohio's contract schedule) and from JLL's 2026 market-by-market time-to-power figures where they do not. The basis is printed beside every year.
Does the table include the capacity charge?
PJM markets carry the BRA clearing price ($333.44 per MW-day for 2027/28, $325.00 for 2028/29) as a separate column. The PJM Capacity Charge Estimator does the bill arithmetic.
Free calculators built on this model
Articles built on this model

Dry Cooler or Cooling Tower: What the Water Bill Says in 15 Markets
A thousand gallons of water and sewer costs $24.80 in Douglas County, Georgia and $8.68 in Baton Rouge as of October 2026, and since a 50 MW open cooling tower needs about 300 million gallons a year, Open Factory's MEP Cost Table puts the gap at $3.6 million a year.

Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line
A prefabricated electrical room for a 50 MW datacenter is not cheaper: Open Factory's Datacenter MEP Cost Table lands the skid route at $3.51M per MW against $3.47M stick-built, 1% more, but 27 weeks faster at 95 weeks from power-block PO to energization against 122, as of August 2026.

What 50 MW Costs in 15 US Markets
A 50 MW connection requested in Northern Virginia in 2026 energizes in 2033 after $75 million of collateral and a 14 year contract, while the same 50 MW in Houston posts no rule-mandated security and can be live in 2028, per Open Factory's Large-Load Cost Table as of August 2026.

Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin
Liquidated damages in public transformer, switchgear and genset contracts run about 0.5% of price a week, capped at 5%, so as of July 2026 a week of delay on a 50 MW datacenter hall costs about $2.7 million against $74,000 of LDs, per Open Factory's Large-Load Cost Table.

How to Write an RFQ for Capital Equipment in 2026
An equipment RFQ in 2026 has to settle escalators, LDs, milestones and tariff refunds: the City of Ocala agreed $8,070,340 for two 105 MVA autotransformers in August 2023 and approved $9,170,340 for the same units on April 28, 2026, a $1.1 million PPI escalator, per Open Factory's Bid-Tab Price Book.

The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT
Texas had about 474 GW of large-load interconnection requests as of August 2026, and ERCOT's March 26, 2026 status table shows 9.0 GW approved to energize and 5.8 GW energized, so about 2% has permission to draw power, as tracked in Open Factory's Large-Load Cost Table.

Reading a Switchgear Quote: The Eleven Line Items That Hide the Schedule
A medium-voltage switchgear quote has eleven line items and four of them move the delivery date more than the price. Riverside Public Utilities paid $2,561,551.88 for one 15 kV metal-clad lineup in June 2024 and it was still in the factory eighteen months later, per Open Factory's Bid-Tab Price Book.

A Factory Owner's Guide to the PJM Capacity Charge
PJM's RTO capacity clearing price rose from $28.92 to $329.17 per MW-day in two auctions, so a 5 MW plant in Met-Ed territory pays about $568,000 for capacity in the delivery year starting June 1, 2026 against about $50,000 in 2024, per Open Factory's PJM Capacity Charge Estimator.

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One slot for a 384 MW GE Vernova 7HA.02 turbine takes a $60 million reservation payment, 20% of a $300 million machine. GE Vernova ended June 2026 with 116 GW under contract, 63 GW as slot reservations, and $25.8 billion paid in advance, which Open Factory's MEP Cost Table carries.

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects and about 2 GW of it runs, or 2.2%, while EIA's July 2026 inventory lists 68.1 GW of planned gas nationwide. Open Factory's Lead-Time Monitor forecasts what energizes by the end of 2028.

Compressed Air Is 10% of Your Factory's Power Bill
Compressed air takes about 10% of a typical plant's electricity by DOE's count, and a 200 hp rotary screw compressor running 6,000 hours a year at the 2025 US industrial rate of 8.62 cents per kWh costs about $70,000 a year. Open Factory finds a leak program worth $83,000.

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant over five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines at 85% utilization and $3.78/MMBtu, with first power in 17, 27 and 30 months, per Open Factory's MEP Cost Table in 2026.

The 2 MW Plant Service Upgrade Nobody Budgets Right
A 400-person plant adding 2 MW of service pays $400k to $1.2M for the items the switchgear quote omits, and with the utility-owned pad-mount at 52 to 104 weeks the crane lands in week 74. Open Factory's Large-Load Cost Table shows the sequencing that pulls energization forward by 20 weeks.

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Between July 2025 and August 2026, 1872, Foundational Industries and Hadrian raised $1.41 billion to build autonomous American factories: $15 million, $25 million and $1.37 billion respectively, with Hadrian's four plants totalling just under 3 million square feet. Open Factory's Lead-Time Monitor will track each one's delivered lead time.

Who Bought the EV Plants' Machines
Companies cancelled, closed or downsized 61 US clean-energy projects worth $34.8 billion in 2025, but most was never built, and the EV plant machines that did reach the secondary market sold at 3% to 37% of reference value in the court records Open Factory read.

When a Megapack Beats a Static UPS
A 24 MW, 48 MWh block of twelve Tesla Megapack 2 XL units costs about $14.4 million installed at January 2026 prices, $10.1 million after the 30% storage credit, against about $17.5 million for the N+1 static UPS in a 20 MW hall, per Open Factory's Datacenter MEP Cost Table.

What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract
Microsoft pays about $112 per MWh for 835 MW from the Crane nuclear restart on a 20-year contract, a 70 to 90% premium to wholesale, so Open Factory's Large-Load Cost Table treats that as the reference price for a 15-year factory power contract as of December 2025.

Datacenter Construction Is Eating Your Electricians
Loudoun County electrical contractor payrolls rose 138% from 5,615 people in 2019 to 14,022 in March 2026, while the national BLS median electrician wage rose 12.5% against 25.6% CPI from May 2019 to May 2025, per Open Factory's Large-Load Cost Table.

The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power
Since July 4, 2025, the 30% federal investment credit survives only for fuel cells among gas-fired on-site power, with wind and solar needing construction by July 4, 2026 and gas CHP getting nothing, and Open Factory's math turns a 2.5-year payback at $210/MWh in California into 1.7 years.

Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First
A generator step-up transformer ordered in the United States was quoted at 143 weeks in the second quarter of 2025, a substation power transformer at 128 weeks and medium-voltage switchgear at 44, per Wood Mackenzie, against about 50 weeks in 2021, and Open Factory's Lead-Time Monitor lists both readings.

Introducing the Large-Load Cost Table: 15 Markets Side by Side
Open Factory's Large-Load Cost Table, version 0.1, compares a 50 MW connection across 15 US utilities on eight tariff cells each: 53 of the 120 cells come from primary documents, 20 from trade press, 2 from arithmetic, and 45 are not published anywhere, as of August 2026.