CalculatorLive

PJM Capacity Charge Estimator

Peak load contribution and zone to the annual capacity charge at the 2025/26 to 2028/29 clearing prices, and what ELRP claws back.

Inputs

Zones with a published base zonal RPM scaling factor in our data. Another zone: pick any and enter the factor under Advanced.
Your average metered kW across PJM's five summer coincident peak hours; your supplier or EDC sends the tag each December.
Advanced and ELRP
From the BRA results workbook, sheet "BRA Load Pricing Results". Leave blank to use the published value.
Curtailable load registered through a curtailment service provider as a Capacity Performance demand resource.
Your contract with the curtailment service provider; 0 shows the gross value.
Annual capacity charge–
Daily UCAP obligation–
Per kW of metered PLC–
ELRP revenue–
Net capacity cost after ELRP–
Same PLC across the four auctions
Delivery yearClearing priceScalingFPRObligationChargeSource

Method and assumptions

Daily UCAP obligation (MW) = PLC at meter x EDC loss multiplier x zonal RPM scaling factor x Forecast Pool Requirement; annual charge = obligation x zonal clearing price ($/MW-day) x days in the delivery year. ELRP gross = nominated MW x DR ELCC x clearing price x days (Manual 18 s4.3).

  1. Clearing prices are the rest-of-RTO Capacity Performance resource clearing prices from PJM's BRA results reports. Constrained LDAs (BGE, DOM, ComEd, EMAAC and others) cleared higher in some years; this tool uses the RTO price for every zone listed.
  2. Base zonal RPM scaling factors and the Forecast Pool Requirement are transcribed from the BRA results workbooks for 2026/27, 2027/28 and 2028/29. For 2025/26 neither is in our data; the tool asks for them.
  3. Loss multipliers: Met-Ed 1.0171 (FirstEnergy PA tariff, Rate GP) and AEP Ohio 1.0552 (primary service). Other zones default to 1.0000, meaning the PLC you enter is already at generation level; enter your EDC's factor.
  4. ELRP: a cleared demand resource is paid the resource clearing price on its accredited UCAP (Manual 18 s4.3). Accreditation uses the DR ELCC PJM published for each auction (69% for 2026/27, 92% for 2027/28); 2028/29 is not in our data. Capacity Performance demand resources must be available for unlimited interruptions in all hours from 2027/28; non-performance charge about $2,280/MWh at the 2027/28 RTO Net CONE, capped at 1.5 x clearing price x days x committed MW.
  5. This is the competitive-supplier PLC pass-through route. Utility default service (for example FirstEnergy PA hourly pricing or AEP Ohio's generation capacity rider) bills capacity differently and can land far from this number.
Auction data as of 2026-09-10.

Method

Daily UCAP obligation = PLC x EDC loss multiplier x base zonal RPM scaling factor x Forecast Pool Requirement, per PJM Manual 18 section 7.5. The annual charge is the obligation times the rest-of-RTO clearing price times the days in the delivery year. Clearing prices come from PJM’s Base Residual Auction reports (2025/26 $269.92, 2026/27 $329.17, 2027/28 $333.44, 2028/29 $325.00 per MW-day), scaling factors and FPR from the BRA results workbooks for 2026/27 to 2028/29. The 2025/26 factors are not in our data and the tool asks for them. ELRP pays the clearing price on nominated MW at the demand-resource ELCC PJM published for each auction (69% for 2026/27, 92% for 2027/28), before the curtailment service provider’s share.

The worked plant in PJM capacity: the factory bill is the default scenario. Every input is mirrored to the URL so a scenario can be shared as a link.

Default assumptions come from the Large-Load Cost Table. Pro subscribers can save inputs. Institutional seats get the underlying series.

Articles that use this calculator

  • The substation transformer and the empty pad beside it, the two things that set an energization year.

    What 50 MW Costs in 15 US Markets

    A 50 MW connection requested in Northern Virginia in 2026 energizes in 2033 after $75 million of collateral and a 14 year contract, while the same 50 MW in Houston posts no rule-mandated security and can be live in 2028, per Open Factory's Large-Load Cost Table as of August 2026.

    Built on the Large-Load Cost Table.

  • The plant floor whose load in five summer hours sets the capacity charge for the following year.

    A Factory Owner's Guide to the PJM Capacity Charge

    PJM's RTO capacity clearing price rose from $28.92 to $329.17 per MW-day in two auctions, so a 5 MW plant in Met-Ed territory pays about $568,000 for capacity in the delivery year starting June 1, 2026 against about $50,000 in 2024, per Open Factory's PJM Capacity Charge Estimator.

    Built on the Large-Load Cost Table.

  • The compressor room of a mid-size plant with two rotary screw packages feeding a common header.

    Compressed Air Is 10% of Your Factory's Power Bill

    Compressed air takes about 10% of a typical plant's electricity by DOE's count, and a 200 hp rotary screw compressor running 6,000 hours a year at the 2025 US industrial rate of 8.62 cents per kWh costs about $70,000 a year. Open Factory finds a leak program worth $83,000.

    Built on the Public Bid-Tab Price Book.

  • The switchgear arrives on the crane while the pad built for the utility's transformer stands empty.

    The 2 MW Plant Service Upgrade Nobody Budgets Right

    A 400-person plant adding 2 MW of service pays $400k to $1.2M for the items the switchgear quote omits, and with the utility-owned pad-mount at 52 to 104 weeks the crane lands in week 74. Open Factory's Large-Load Cost Table shows the sequencing that pulls energization forward by 20 weeks.

    Built on the Large-Load Cost Table.

  • A twelve-unit battery block on its gravel pad outside a data hall, tied to the building through medium-voltage switchgear.

    When a Megapack Beats a Static UPS

    A 24 MW, 48 MWh block of twelve Tesla Megapack 2 XL units costs about $14.4 million installed at January 2026 prices, $10.1 million after the 30% storage credit, against about $17.5 million for the N+1 static UPS in a 20 MW hall, per Open Factory's Datacenter MEP Cost Table.

    Built on the Datacenter MEP Cost Table.

  • A shut reactor's turbine hall during the work of bringing the unit back to service.

    What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract

    Microsoft pays about $112 per MWh for 835 MW from the Crane nuclear restart on a 20-year contract, a 70 to 90% premium to wholesale, so Open Factory's Large-Load Cost Table treats that as the reference price for a 15-year factory power contract as of December 2025.

    Built on the Large-Load Cost Table.

  • An electrical room under rough-in at a datacenter campus, with the pulling crew working the feeder run.

    Datacenter Construction Is Eating Your Electricians

    Loudoun County electrical contractor payrolls rose 138% from 5,615 people in 2019 to 14,022 in March 2026, while the national BLS median electrician wage rose 12.5% against 25.6% CPI from May 2019 to May 2025, per Open Factory's Large-Load Cost Table.

    Built on the Large-Load Cost Table.

  • A ten-megawatt fuel-cell installation on a factory pad, fed by a natural-gas service line rather than the utility's wires.

    The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power

    Since July 4, 2025, the 30% federal investment credit survives only for fuel cells among gas-fired on-site power, with wind and solar needing construction by July 4, 2026 and gas CHP getting nothing, and Open Factory's math turns a 2.5-year payback at $210/MWh in California into 1.7 years.

    Built on the Datacenter MEP Cost Table.

  • A substation yard part-built for a new large load, with the transformer pad poured and empty.

    Introducing the Large-Load Cost Table: 15 Markets Side by Side

    Open Factory's Large-Load Cost Table, version 0.1, compares a 50 MW connection across 15 US utilities on eight tariff cells each: 53 of the 120 cells come from primary documents, 20 from trade press, 2 from arithmetic, and 45 are not published anywhere, as of August 2026.

    Built on the Large-Load Cost Table.

  • A datacenter generator yard with its last four pads still empty and no units on site to fill them.

    Cummins and Caterpillar Are Sold Out Through 2028

    Cummins is taking generator orders well into 2028 and Caterpillar closed June 2026 with $72.1 billion of firm backlog, and Open Factory's Lead-Time Monitor shows published lead times of 50 to 66 weeks for a 1,500 to 2,000 kW diesel genset and 90 to 110 weeks above 3,500 kW.

    Built on the Lead-Time Monitor.