ReferenceLead times by equipment class

Distribution and pad-mount transformer lead time: 104 or more weeks

Distribution and pad-mount transformer: how long is the lead time?

In short. Distribution and pad-mount transformer is quoted at 104 or more weeks, per NRECA coalition letter, Jan 4 2024. "More than two years" per the NRECA coalition letter of Jan 4 2024; Wood Mackenzie reported pad-mount lead times still rising in Q2 2025. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

Facts

Equipment classDistribution and pad-mount transformer
GroupTransformers and MV gear, industry averages
Published lead time104 or more weeks
Basis"More than two years" per the NRECA coalition letter of Jan 4 2024; Wood Mackenzie reported pad-mount lead times still rising in Q2 2025
Published byNRECA coalition letter, Jan 4 2024
Document dateJanuary 4, 2024
What public buyers paidmedians from $27.92 to $267.73 per kVA across 15 published bands (413 awards, January 2020 to August 2026)
HTS line and duty8504.22.00, Liquid-filled transformer, 650 to 10,000 kVA (pad-mount, substation); 50% from China, 25% from Mexico, 25% from EU, 25% from Korea all-in as of September 9, 2026
Data as ofSeptember 2, 2026

Questions

Distribution and pad-mount transformer: how long is the lead time?

104 or more weeks, per NRECA coalition letter, Jan 4 2024. "More than two years" per the NRECA coalition letter of Jan 4 2024; Wood Mackenzie reported pad-mount lead times still rising in Q2 2025.

Who published this lead time?

NRECA coalition letter, Jan 4 2024. This is a third-party survey average, labelled as theirs. Open Factory reprints it with the document and its date.

Distribution and pad-mount transformer: what does it cost?

Public awards: medians from $27.92 to $267.73 per kVA across 15 published bands (413 awards, January 2020 to August 2026), from Open Factory's Public Bid-Tab Price Book as of September 1, 2026.

Distribution and pad-mount transformer: what import duty applies?

HTS 8504.22.00: 50% from China, 25% from Mexico, 25% from EU, 25% from Korea all-in, as of September 9, 2026.

How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

Sources

  1. Open Factory Lead-Time Monitor
  2. NRECA coalition letter, Jan 4 2024

Data as of September 2, 2026. This page is rebuilt from the same table the Lead-Time-Adjusted Schedule, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Distribution and pad-mount transformer lead time: 104 or more weeks, September 2, 2026.