ReferenceLead times by equipment class

LV power circuit breaker, MTZ/NW/P/R frames lead time: 20 to 24 weeks

LV power circuit breaker, MTZ/NW/P/R frames: how long is the lead time?

In short. LV power circuit breaker, MTZ/NW/P/R frames is quoted at 20 to 24 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 5 product rows, made-to-order weeks from release to manufacturing. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

Facts

Equipment classLV power circuit breaker, MTZ/NW/P/R frames (Schneider)
GroupSchneider Electric Lead Times Guide
Published lead time20 to 24 weeks
Basis5 product rows, made-to-order weeks from release to manufacturing
Published bySchneider Electric Lead Times Guide, September 2026 edition
Document dateSeptember 2, 2026
Data as ofSeptember 2, 2026

Questions

LV power circuit breaker, MTZ/NW/P/R frames: how long is the lead time?

20 to 24 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 5 product rows, made-to-order weeks from release to manufacturing.

Who published this lead time?

Schneider Electric Lead Times Guide, September 2026 edition. This is the OEM's own planning figure for made-to-order product, not a quote. Open Factory reprints it with the document and its date.

How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

Sources

  1. Open Factory Lead-Time Monitor
  2. Schneider Electric Lead Times Guide, September 2026 edition

Data as of September 2, 2026. This page is rebuilt from the same table the Lead-Time-Adjusted Schedule, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, LV power circuit breaker, MTZ/NW/P/R frames lead time: 20 to 24 weeks, September 2, 2026.