# LV power circuit breaker, MTZ/NW/P/R frames lead time: 20 to 24 weeks

URL: https://open-factory.com/lead-times/lv-power-breaker/
Data as of: 2026-09-02
Publisher: Open Factory, https://open-factory.com

**LV power circuit breaker, MTZ/NW/P/R frames: how long is the lead time?** LV power circuit breaker, MTZ/NW/P/R frames is quoted at 20 to 24 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 5 product rows, made-to-order weeks from release to manufacturing. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

## Facts

- Equipment class: LV power circuit breaker, MTZ/NW/P/R frames (Schneider)
- Group: Schneider Electric Lead Times Guide
- Published lead time: 20 to 24 weeks
- Basis: 5 product rows, made-to-order weeks from release to manufacturing
- Published by: Schneider Electric Lead Times Guide, September 2026 edition (https://www.se.com/us/en/download/document/Monthly_Lead/)
- Document date: September 2, 2026
- Data as of: September 2, 2026

## Questions

### LV power circuit breaker, MTZ/NW/P/R frames: how long is the lead time?

20 to 24 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 5 product rows, made-to-order weeks from release to manufacturing.

### Who published this lead time?

Schneider Electric Lead Times Guide, September 2026 edition. This is the OEM's own planning figure for made-to-order product, not a quote. Open Factory reprints it with the document and its date.

### How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

## Related articles

- [The Recommended Spares List Is Where the Margin Hides](https://open-factory.com/articles/recommended-spares-margin/)
- [Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line](https://open-factory.com/articles/skids-vs-stick-built/)
- [What 50 MW Costs in 15 US Markets](https://open-factory.com/articles/what-50mw-costs-15-markets/)
- [The $306k Machine: A Record Half-Year With Fewer Units](https://open-factory.com/articles/machine-tool-record-fewer-units/)
- [The $60 Million Deposit: How Equipment Slots Became Datacenter Currency](https://open-factory.com/articles/slot-economy/)
- [Compressed Air Is 10% of Your Factory's Power Bill](https://open-factory.com/articles/compressed-air-10-percent/)

## Sources

- [Open Factory Lead-Time Monitor](https://open-factory.com/models/lead-time-monitor/)
- [Schneider Electric Lead Times Guide, September 2026 edition](https://www.se.com/us/en/download/document/Monthly_Lead/)

Model: https://open-factory.com/models/lead-time-monitor/
Calculator: https://open-factory.com/tools/lead-time-schedule/