Genset 1500 to 2000 kW, diesel lead time: 50 to 66 weeks
Genset 1500 to 2000 kW, diesel: how long is the lead time?
In short. Genset 1500 to 2000 kW, diesel is quoted at 50 to 66 weeks, per Terrapin Construction Group (June 10, 2026). Terrapin Construction Group (GC slot reservations). Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.
Facts
| Equipment class | Genset 1500 to 2000 kW, diesel |
|---|---|
| Group | Gensets and transfer switches (published by contractors and OEMs) |
| Published lead time | 50 to 66 weeks |
| Basis | Terrapin Construction Group (GC slot reservations) |
| Published by | Terrapin Construction Group |
| Document date | June 10, 2026 |
| HTS line and duty | 8502.13.00, Diesel generating set over 375 kVA; 39.5% from China, 0% from Mexico, 10% from EU, 10.5% from Korea all-in as of September 9, 2026 |
| Data as of | September 2, 2026 |
Questions
Genset 1500 to 2000 kW, diesel: how long is the lead time?
50 to 66 weeks, per Terrapin Construction Group, dated June 10, 2026. Terrapin Construction Group (GC slot reservations).
Who published this lead time?
Terrapin Construction Group. This is the publisher's own figure, labelled as theirs. Open Factory reprints it with the document and its date.
Genset 1500 to 2000 kW, diesel: what import duty applies?
HTS 8502.13.00: 39.5% from China, 0% from Mexico, 10% from EU, 10.5% from Korea all-in, as of September 9, 2026.
How often is this page updated?
Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.