# Genset 1500 to 2000 kW, diesel lead time: 50 to 66 weeks

URL: https://open-factory.com/lead-times/genset-1500-to-2000-kw/
Data as of: 2026-09-02
Publisher: Open Factory, https://open-factory.com

**Genset 1500 to 2000 kW, diesel: how long is the lead time?** Genset 1500 to 2000 kW, diesel is quoted at 50 to 66 weeks, per Terrapin Construction Group (June 10, 2026). Terrapin Construction Group (GC slot reservations). Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

## Facts

- Equipment class: Genset 1500 to 2000 kW, diesel
- Group: Gensets and transfer switches (published by contractors and OEMs)
- Published lead time: 50 to 66 weeks
- Basis: Terrapin Construction Group (GC slot reservations)
- Published by: Terrapin Construction Group (https://terrapincg.com/news/switchgear-transformer-generator-lead-times-2026)
- Document date: June 10, 2026
- HTS line and duty: 8502.13.00, Diesel generating set over 375 kVA; 39.5% from China, 0% from Mexico, 10% from EU, 10.5% from Korea all-in as of September 9, 2026 (https://open-factory.com/tariffs/8502-13-00/)
- Data as of: September 2, 2026

## Questions

### Genset 1500 to 2000 kW, diesel: how long is the lead time?

50 to 66 weeks, per Terrapin Construction Group, dated June 10, 2026. Terrapin Construction Group (GC slot reservations).

### Who published this lead time?

Terrapin Construction Group. This is the publisher's own figure, labelled as theirs. Open Factory reprints it with the document and its date.

### Genset 1500 to 2000 kW, diesel: what import duty applies?

HTS 8502.13.00: 39.5% from China, 0% from Mexico, 10% from EU, 10.5% from Korea all-in, as of September 9, 2026.

### How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

## Related articles

- [The Recommended Spares List Is Where the Margin Hides](https://open-factory.com/articles/recommended-spares-margin/)
- [Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin](https://open-factory.com/articles/liquidated-damages/)
- [How to Write an RFQ for Capital Equipment in 2026](https://open-factory.com/articles/rfq-capital-equipment/)
- [The Used and Refurbished Market Nobody Indexes](https://open-factory.com/articles/used-refurbished-market/)
- [Quote Check: What Your Switchgear Quote Should Have Said](https://open-factory.com/articles/quote-check-launch/)
- [Tariff Bill of Materials: What Sections 232 and 301 Add to a UPS, a Lineup, a Genset and a Megapack](https://open-factory.com/articles/tariff-bom-electrical/)

## Sources

- [Open Factory Lead-Time Monitor](https://open-factory.com/models/lead-time-monitor/)
- [Terrapin Construction Group](https://terrapincg.com/news/switchgear-transformer-generator-lead-times-2026)

Model: https://open-factory.com/models/lead-time-monitor/
Calculator: https://open-factory.com/tools/lead-time-schedule/