ReferenceLarge-load power by market

West and South Texas: what a 50 MW connection costs under AEP Texas

What does a 50 MW connection cost in West and South Texas?

In short. In West and South Texas, AEP Texas connects a 50 MW load under same ERCOT/PUCT regime as Oncor, docket PUCT Project 58481. Minimum bill: none by rule (AEP cites take-or-pay ESAs for its vertically integrated utilities; AEP Texas is wires-only). Term: none by rule. Realistic energization: 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketWest and South Texas, TX (ERCOT)
UtilityAEP Texas
Tariff or rulesame ERCOT/PUCT regime as Oncor
DocketPUCT Project 58481; Batch Zero
Statusas Oncor
Large-load threshold75 MW (SB 6)
Study feeTDSP study (fee not published)
Security or collateralAEP contracts are take-or-pay electric service agreements at the AEP level; AEP Texas terms not public
Minimum billnone by rule (AEP cites take-or-pay ESAs for its vertically integrated utilities; AEP Texas is wires-only)
Contract termnone by rule
Rampnone by rule
Exit feeas Oncor for 75 MW+
CIAC exposureas Oncor; AEP Texas funding ~100 transmission projects with a $3.26B DOE loan
Realistic energization, 50 MW2029
VerificationPARTIAL (regime verified; AEP Texas queue and fees not public)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in West and South Texas?

AEP Texas: study fee TDSP study (fee not published); collateral AEP contracts are take-or-pay electric service agreements at the AEP level; AEP Texas terms not public; minimum bill none by rule (AEP cites take-or-pay ESAs for its vertically integrated utilities; AEP Texas is wires-only); term none by rule.

When can a 50 MW load be energized in West and South Texas?

2029. AEP added 6 GW of signed load agreements in Q2 2026 mostly in Texas; 765 kV Permian lines targeted for December 2028; Batch Zero plan fall 2027.

Which tariff applies to large loads in West and South Texas?

same ERCOT/PUCT regime as Oncor; docket PUCT Project 58481; Batch Zero; status: as Oncor.

Is this rate proposed or approved?

Approved or in effect as of the data date (as Oncor). PARTIAL (regime verified; AEP Texas queue and fees not public).

Sources

  1. Open Factory Large-Load Cost Table
  2. aep.com (2026-07-30)
  3. utilitydive.com (2026-01-06)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, West and South Texas: what a 50 MW connection costs under AEP Texas, August 21, 2026.