ReferenceLarge-load power by market

Houston: what a 50 MW connection costs under CenterPoint Energy Houston Electric

What does a 50 MW connection cost in Houston?

In short. In Houston, CenterPoint Energy Houston Electric connects a 50 MW load under same ERCOT/PUCT regime as Oncor; facility extension agreements with deposits below 75 MW, docket PUCT Project 58481. Minimum bill: none. Term: none. Realistic energization: 2028 to 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketHouston, TX (ERCOT)
UtilityCenterPoint Energy Houston Electric
Tariff or rulesame ERCOT/PUCT regime as Oncor; facility extension agreements with deposits below 75 MW
DocketPUCT Project 58481; Batch Zero
Statusas Oncor
Large-load threshold75 MW (SB 6); 25 MW for community-impact review
Study feeTDSP study (fee not published)
Security or collateralfacility extension agreements with customer cash commitments and deposits: about $900 million against 14 GW of Batch Zero-eligible load
Minimum billnone
Contract termnone
Rampnone required by rule
Exit feeforfeiture terms in facility extension agreements (not public)
CIAC exposurecustomer-funded extension facilities under the TDSP tariff; 100% direct interconnection CIAC at 75 MW+ (proposed)
Realistic energization, 50 MW2028 to 2029
VerificationPARTIAL (company statements verified; tariff sheet not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Houston?

CenterPoint Energy Houston Electric: study fee TDSP study (fee not published); collateral facility extension agreements with customer cash commitments and deposits: about $900 million against 14 GW of Batch Zero-eligible load; minimum bill none; term none.

When can a 50 MW load be energized in Houston?

2028 to 2029. CenterPoint: 3.5 GW under construction; 8 GW of data center load energized by 2029 and nearly all 14 GW by end-2030; 90% of projects at or under 500 MW sited near existing substations; JLL puts Texas (Dallas) at ~2.5 years for 50 MW.

Which tariff applies to large loads in Houston?

same ERCOT/PUCT regime as Oncor; facility extension agreements with deposits below 75 MW; docket PUCT Project 58481; Batch Zero; status: as Oncor.

Is this rate proposed or approved?

Approved or in effect as of the data date (as Oncor). PARTIAL (company statements verified; tariff sheet not opened).

Sources

  1. Open Factory Large-Load Cost Table
  2. utilitydive.com (2026-07-28)
  3. utilitydive.com (2026-04-23)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Houston: what a 50 MW connection costs under CenterPoint Energy Houston Electric, August 21, 2026.