Book-to-Bill League Table
Quarterly orders, backlog and book-to-bill for every listed electrical, power and cooling OEM, from filings only, with the read-across for buyers: which classes are getting longer and which are clearing.
3.0 xPowell Industries book-to-bill, quarter ended June 30 2026: $934M of orders on $312M of revenue. Public headline as of August 3, 2026.
- 3.0x
- Powell Industries, orders $934M on revenue $312M, backlog $2.4B (+69% YoY), 8-K Ex. 99.1, August 3 2026
- $72.1B
- Caterpillar company backlog at June 30 2026, +92% YoY, $29.2B beyond twelve months, 10-Q
- 1.48
- Siemens Energy Grid Technologies, Q3 FY2026, backlog EUR 51bn, transformers the largest contributor
- 18
- OEMs tracked each quarter; 8 disclose enough to compute a ratio, 9 disclose backlog in dollars
What it covers
Eighteen listed OEMs each calendar quarter: Eaton, Vertiv, Schneider Electric, ABB, Siemens Energy, GE Vernova, Hitachi Energy, Powell, Generac, Caterpillar, Cummins, Trane Technologies, Carrier, Johnson Controls, nVent, Modine, Hubbell and Atkore. Orders, revenue, backlog, book-to-bill with its basis (reported or derived, quarter or rolling), backlog change, and the datacenter commentary, each row linked to the 8-K, 10-Q or earnings release it came from.
- Cadence
- Quarterly, within two weeks of the last filing in the set
- Compiled from
- 8-K earnings exhibits, 10-Q and 10-K filings on sec.gov; Siemens Energy, ABB, Schneider Electric and Hitachi earnings releases and analyst presentations; FRED DEXUSEU for euro conversion; XBRL companyfacts for deferred revenue
- Delivered as
- Excel workbook, Web dashboard
- Updates
- Quarterly updates, one year included
- Onboarding
- Onboarding call
- Support
- Ad hoc analyst calls
- Tier
- Headline free; table Pro
Who uses it and what it decides
- Buyers planning capital projectsWhether lead times in a class will lengthen or shorten next quarter, before the OEM tells them.
- Estimators and sourcing managersWhich OEM has room in its book this quarter and which is turning work away.
- Equity and credit analystsOne table instead of eighteen investor decks, with the basis of every ratio spelled out.
Methodology
What the headline is
3.0x is Powell Industries’ reported book-to-bill for the quarter ended June 30 2026: orders of $934 million against revenue of $311.7 million, backlog $2.4 billion, up 69% on a year earlier, in the Q3 FY2026 earnings release filed 3 August 2026. The 10-Q says $1.3 billion of that backlog ships within twelve months. The next seven: Hitachi Energy 2.09 (derived, yen), GE Vernova Electrification 1.75, Siemens Energy Grid Technologies 1.48, Caterpillar about 1.46 (implied from the backlog change), ABB Electrification 1.39, Trane 1.23, Eaton Electrical 1.2 (rolling twelve months). The rows are in book-to-bill-q2-2026.csv.
The headline is the highest ratio in the quarter with its basis stated. A derived ratio can lead only if the orders and revenue figures are both reported.
What it is compiled from
Version 0.1 is filings only. Nothing is asked of any company.
- Reported ratios: Powell (quarter), Siemens Energy (quarter), Trane (quarter, “123%”), Eaton (rolling twelve months).
- Derived ratios: orders divided by revenue where both are reported: GE Vernova ($6,347M / $3,637M), ABB ($7,231M / $5,200M), Hitachi (1,906.3 / 911.9 billion yen).
- Implied ratio: Caterpillar, from the change in company backlog plus sales over sales, labelled implied.
- Backlog in dollars: Caterpillar $72.1B, Hitachi Energy $63.6B (10.3 trillion yen at Hitachi’s translation), Siemens Energy GT $58.2B (EUR 51bn at 1.1417 DEXUSEU, June 30 2026), GE Vernova Electrification $40.6B, Johnson Controls $21.0B, ABB Electrification $13.7B, Trane $12.1B, Powell $2.4B, Generac about $1.6B (data center products only).
- Not disclosed, and said so: Vertiv (deferred revenue $3,633.7M is tracked instead, from XBRL companyfacts), Schneider Electric (“record backlog”, no figure), Carrier (orders growth only), Cummins, nVent (Q1 only), Modine, Hubbell, Atkore.
What is free and what is paid
- Free: the headline ratio, this page, and the ranked chart in Book-to-Bill League Table, Q2 2026.
- Pro: the eighteen-row table each quarter with orders, revenue, backlog, basis, backlog change and datacenter commentary, plus the quarter-by-quarter series back to Q3 2025.
- Institutional: the workbook with every filing linked, the dashboard, the API, quarterly updates for a year, an onboarding call and ad hoc calls.
Articles built on it
Book-to-Bill League Table, Q2 2026: Every Electrical OEM, Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate, Cummins and Caterpillar Are Sold Out Through 2028 and The $60 Million Deposit. The disclosure behaviour of the same eighteen companies is scored on the OEM Disclosure Scorecard.
Version history
- 0.1 (September 2026). Eighteen OEMs, calendar quarters Q4 2025 to Q2 2026. Euro and yen conversions at quarter-end FRED rates or the company’s own translation, stated per row.
What version 1 adds
Private OEMs from interviews (with the count printed only when true), segment-level ratios where an OEM reports them on the call but not in the release, and a lead-time read-across column that maps each OEM’s backlog months to the classes in the Lead-Time Monitor.
Known gaps
Johnson Controls reports orders as growth only, so no ratio is derivable. Eaton’s ratio is not comparable to the quarterly ones and is ranked separately. Generac’s backlog is data center products only and excludes its second hyperscaler agreement. Hitachi’s yen backlog is translated at Hitachi’s own rate.
Questions
Why does Eaton show 1.2 and Powell 3.0 when both are booking record orders?
Different bases. Eaton reports a rolling twelve-month ratio for its Electrical businesses; Powell reports the quarter. The table prints the basis beside every number and never mixes them in a ranking without saying so.
Where is Vertiv?
In the table with 'not disclosed' in the orders and backlog cells since the Q1 2026 release. Its last disclosed backlog was $15.0B at December 31 2025. Our estimate from deferred revenue is a separate piece, Vertiv Stopped Reporting Its Backlog.
Do you include private OEMs?
Not in version 0.1. Filings only. Private OEMs (Virginia Transformer, SPX, Rehlko, Munters' US unit) come with interviews in a later version.
Articles built on this model

Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line
A prefabricated electrical room for a 50 MW datacenter is not cheaper: Open Factory's Datacenter MEP Cost Table lands the skid route at $3.51M per MW against $3.47M stick-built, 1% more, but 27 weeks faster at 95 weeks from power-block PO to energization against 122, as of August 2026.

800 VDC Will Strand Your White-Space Frame Agreement
NVIDIA set a ship date for 800 VDC on August 11, 2026, with the MGX power rack due in the second half of 2026. Open Factory finds a five-year 415 V UPS and AC busway frame agreement puts 40 to 60% of its dollars into superseded SKUs.

Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin
Liquidated damages in public transformer, switchgear and genset contracts run about 0.5% of price a week, capped at 5%, so as of July 2026 a week of delay on a 50 MW datacenter hall costs about $2.7 million against $74,000 of LDs, per Open Factory's Large-Load Cost Table.

The R-454B Summer: What the Refrigerant Switch Did to Chiller Prices
A 20 lb cylinder of R-454B cost $345 in 2021 and $700 to $2,000 in July and August 2025, the switch raised Carrier chiller list prices 10% in March 2024 and March 2025, and Open Factory finds the 563 lb charge in a 500-ton chiller is 1.2% of the machine.

OFCI vs Design-Build: How Hyperscalers Buy Chillers and Colo Developers Do Not
Owner-furnished, contractor-installed chillers and CDUs for a 20 MW liquid-cooled hall cost $27.9 million against $32.8 million through the mechanical subcontract, a saving of $4.9 million or 14.9%, because OFCI strips a 15% subcontractor markup and 10% GC fee, per Open Factory's Datacenter MEP Cost Table as of June 2026.

From 36 Weeks to Stock: The ControlLogix Lead-Time Cycle
Rockwell's own bulletin listed a ControlLogix 5580 controller at 35 calendar days on September 22, 2021 and 208 days on October 26, 2022, and Open Factory's Lead-Time Monitor, which holds eleven editions of that bulletin, now reads the PLC line at stock.

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One slot for a 384 MW GE Vernova 7HA.02 turbine takes a $60 million reservation payment, 20% of a $300 million machine. GE Vernova ended June 2026 with 116 GW under contract, 63 GW as slot reservations, and $25.8 billion paid in advance, which Open Factory's MEP Cost Table carries.

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects and about 2 GW of it runs, or 2.2%, while EIA's July 2026 inventory lists 68.1 GW of planned gas nationwide. Open Factory's Lead-Time Monitor forecasts what energizes by the end of 2028.

Five Majors Bought Their Way Into Liquid Cooling. Here Is the Price List
Five majors paid $16.3 billion of disclosed prices for liquid cooling companies in seventeen months, with Ecolab buying CoolIT for $4.75 billion at 29 times EBITDA on March 20, 2026 and Eaton closing Boyd Thermal at $9.5 billion and 22.5 times, per Open Factory's deal table.

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant over five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines at 85% utilization and $3.78/MMBtu, with first power in 17, 27 and 30 months, per Open Factory's MEP Cost Table in 2026.

Chillers Are the 60-Week Problem
A water-cooled chiller over 1,000 tons quotes at 50 to 70 weeks in the United States as of May 22, 2026, an air-cooled machine over 500 tons at 40 to 60 weeks, and Census M3 puts HVAC unfilled orders at $18.6 billion in July 2026, per Open Factory's Lead-Time Monitor.

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Between July 2025 and August 2026, 1872, Foundational Industries and Hadrian raised $1.41 billion to build autonomous American factories: $15 million, $25 million and $1.37 billion respectively, with Hadrian's four plants totalling just under 3 million square feet. Open Factory's Lead-Time Monitor will track each one's delivered lead time.

Who Bought the EV Plants' Machines
Companies cancelled, closed or downsized 61 US clean-energy projects worth $34.8 billion in 2025, but most was never built, and the EV plant machines that did reach the secondary market sold at 3% to 37% of reference value in the court records Open Factory read.

The OEM Disclosure Scorecard: Who Tells Buyers Anything
Open Factory's OEM Disclosure Scorecard version 0.1 finds that the eighteen largest electrical, power and cooling OEMs publish only 12 of 90 cells a buyer needs, with 16 Partials and 62 Noes: GE Vernova alone scores 2 of 5, ten score 1 and seven score 0, as of September 2026.

Rockwell's 250 Basis Points: How Tariffs Show Up in Your PLC Quote
Tariffs are 100 basis points of a Rockwell Automation bill in fiscal 2026, inside the 250 basis points of total price the company guided on its August 4, 2026 call, and Open Factory's Bid-Tab Price Book tracks the pass-through against the 150 basis points of underlying price.

Why Your Switchgear Costs 50% More Than in 2021
The BLS producer price index for switchgear stood at 394.8 in July 2026, 78% above January 2021, and medium-voltage switchgear is up 50% since 2021 per Wood Mackenzie. Open Factory's decomposition finds inputs explain 36 of the 78 points and margin the other 43.

Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate
Open Factory estimates Vertiv's unpublished order backlog at $16 to $20 billion at June 30, 2026, central case about $17.4 billion, up from the last reported $15.0 billion at December 31, 2025, with current deferred revenue doubling from $1.81 billion to $3.63 billion in six months.

Transformer Lead Times Hit 143 Weeks: Who Gets Delivered First
A generator step-up transformer ordered in the United States was quoted at 143 weeks in the second quarter of 2025, a substation power transformer at 128 weeks and medium-voltage switchgear at 44, per Wood Mackenzie, against about 50 weeks in 2021, and Open Factory's Lead-Time Monitor lists both readings.

One Steel Mill Gates Every US Transformer
Every pound of domestic grain-oriented electrical steel in a US transformer core is melted at Cleveland-Cliffs Butler Works, a plant with a 920 mm maximum coil width, and the transformer PPI is up 91% since December 2019 at 381.8 in July 2026, per Open Factory's Lead-Time Monitor.

MES Is a Consulting Product
The Bureau of Engraving and Printing has paid $110.1 million for MES support services since May 2021 against $4.64 million of Oracle licences in FY2025, about five dollars of consulting per dollar of software, the pattern Open Factory found across 44 public MES and SCADA awards as of October 2025.

The $2,850 Report That Says Nothing
IBISWorld's $2,850 ProcurementIQ switchgear report prices the whole category at one $37,300 benchmark, while the 118 public awards in Open Factory's Public Bid-Tab Price Book run from $12,492 for a pad-mount switch in 2019 to $3,827,000 for a 34.5 kV lineup in September 2024.

Cummins and Caterpillar Are Sold Out Through 2028
Cummins is taking generator orders well into 2028 and Caterpillar closed June 2026 with $72.1 billion of firm backlog, and Open Factory's Lead-Time Monitor shows published lead times of 50 to 66 weeks for a 1,500 to 2,000 kW diesel genset and 90 to 110 weeks above 3,500 kW.

The 171-Day Capex Lead Time: ISM's Most Ignored Table
The average US manufacturing buyer commits to capital equipment 171 days ahead of need in the August 2026 ISM report, with 27% committing more than a year out, against 147 days in December 2019. Open Factory's Lead-Time Monitor rebuilds the series back to 2007.

Book-to-Bill League Table, Q2 2026: Every Electrical OEM
Powell Industries posted a book-to-bill of 3.0 in the quarter to June 30 2026, booking $934 million of switchgear orders against $312 million shipped, and all eight electrical OEMs that print a ratio sit above 1.0, down to Eaton at 1.2, in Open Factory's Book-to-Bill League Table.

Introducing the Open Factory Lead-Time Monitor
Schneider Electric quotes low-voltage switchgear at 50 weeks from release to manufacturing in its September 2026 Lead Times Guide, and Open Factory's Lead-Time Monitor, launched as version 0.1, puts all eleven equipment classes in one table, of which only four have an OEM-published lead time.