ReferenceLead times by equipment class

Power transformer, 5 MVA and up lead time: 128 weeks

Power transformer, 5 MVA and up: how long is the lead time?

In short. Power transformer, 5 MVA and up is quoted at 128 weeks, per Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). Average quoted lead time, Q2 2025; 2024 range 80 to 210 weeks for large units. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

Facts

Equipment classPower transformer, 5 MVA and up (industry average)
GroupTransformers and MV gear, industry averages
Published lead time128 weeks
BasisAverage quoted lead time, Q2 2025; 2024 range 80 to 210 weeks for large units
Published byWood Mackenzie T&D supply chain note, Oct 15 2025 (as reported)
Document date2025 Q2
What public buyers paidmedian $2,132,514 per unit (6 awards, March 2024 to August 2026, 34.5 to 99 kV class (69 kV typical), per unit)
HTS line and duty8504.23.00, Liquid-filled transformer over 10,000 kVA (LPT, GSU); 40% from China, 13.4% from Mexico, 15% from EU, 13.4% from Korea all-in as of September 9, 2026
Data as ofSeptember 2, 2026

Questions

Power transformer, 5 MVA and up: how long is the lead time?

128 weeks, per Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). Average quoted lead time, Q2 2025; 2024 range 80 to 210 weeks for large units.

Who published this lead time?

Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). This is a third-party survey average, labelled as theirs. Open Factory reprints it with the document and its date.

Power transformer, 5 MVA and up: what does it cost?

Public awards: median $2,132,514 per unit (6 awards, March 2024 to August 2026, 34.5 to 99 kV class (69 kV typical), per unit), from Open Factory's Public Bid-Tab Price Book as of September 1, 2026.

Power transformer, 5 MVA and up: what import duty applies?

HTS 8504.23.00: 40% from China, 13.4% from Mexico, 15% from EU, 13.4% from Korea all-in, as of September 9, 2026.

How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

Sources

  1. Open Factory Lead-Time Monitor

Data as of September 2, 2026. This page is rebuilt from the same table the Lead-Time-Adjusted Schedule, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Power transformer, 5 MVA and up lead time: 128 weeks, September 2, 2026.