ReferenceLead times by equipment class

Generator step-up transformer lead time: 143 weeks

Generator step-up transformer: how long is the lead time?

In short. Generator step-up transformer is quoted at 143 weeks, per Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). Average quoted lead time, Q2 2025. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

Facts

Equipment classGenerator step-up transformer (industry average)
GroupTransformers and MV gear, industry averages
Published lead time143 weeks
BasisAverage quoted lead time, Q2 2025
Published byWood Mackenzie T&D supply chain note, Oct 15 2025 (as reported)
Document date2025 Q2
Data as ofSeptember 2, 2026

Questions

Generator step-up transformer: how long is the lead time?

143 weeks, per Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). Average quoted lead time, Q2 2025.

Who published this lead time?

Wood Mackenzie T&D supply chain note, Oct 15 2025 (as reported). This is a third-party survey average, labelled as theirs. Open Factory reprints it with the document and its date.

How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

Sources

  1. Open Factory Lead-Time Monitor

Data as of September 2, 2026. This page is rebuilt from the same table the Lead-Time-Adjusted Schedule, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Generator step-up transformer lead time: 143 weeks, September 2, 2026.