ReferenceLead times by equipment class

Genset 1000 to 3000 kW, natural gas lead time: 54 to 78 weeks

Genset 1000 to 3000 kW, natural gas: how long is the lead time?

In short. Genset 1000 to 3000 kW, natural gas is quoted at 54 to 78 weeks, per Terrapin Construction Group (June 10, 2026). Terrapin Construction Group (GC slot reservations). Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

Facts

Equipment classGenset 1000 to 3000 kW, natural gas
GroupGensets and transfer switches (published by contractors and OEMs)
Published lead time54 to 78 weeks
BasisTerrapin Construction Group (GC slot reservations)
Published byTerrapin Construction Group
Document dateJune 10, 2026
Data as ofSeptember 2, 2026

Questions

Genset 1000 to 3000 kW, natural gas: how long is the lead time?

54 to 78 weeks, per Terrapin Construction Group, dated June 10, 2026. Terrapin Construction Group (GC slot reservations).

Who published this lead time?

Terrapin Construction Group. This is the publisher's own figure, labelled as theirs. Open Factory reprints it with the document and its date.

How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

Sources

  1. Open Factory Lead-Time Monitor
  2. Terrapin Construction Group

Data as of September 2, 2026. This page is rebuilt from the same table the Lead-Time-Adjusted Schedule, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Genset 1000 to 3000 kW, natural gas lead time: 54 to 78 weeks, September 2, 2026.