ReferenceLarge-load power by market

Salt Lake City: what a 50 MW connection costs under PacifiCorp / Rocky Mountain Power

What does a 50 MW connection cost in Salt Lake City?

In short. In Salt Lake City, PacifiCorp / Rocky Mountain Power connects a 50 MW load under Utah SB 132 (2025) large-load pathways; Large-Load Service Contract approved by Utah PSC; Oregon Schedule 401 pending under HB 3546, docket Utah PSC 26-035-05 (approved). Minimum bill: not published. Term: not published. Realistic energization: 2028 to 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketSalt Lake City, UT (PacifiCorp (non-RTO; EDAM))
UtilityPacifiCorp / Rocky Mountain Power
Tariff or ruleUtah SB 132 (2025) large-load pathways; Large-Load Service Contract approved by Utah PSC; Oregon Schedule 401 pending under HB 3546
DocketUtah PSC 26-035-05 (approved); OPUC UE 463 (pending)
Statusapproved (Utah contract form); Oregon pending
Large-load threshold100 MW within five years (SB 132)
Study feenot published
Security or collateralnot published
Minimum billnot published
Contract termnot published
Rampnot published
Exit feenot published
CIAC exposureSB 132: loads using separate generation pay interconnection and transmission studies plus system upgrades and the transmission rate; RMP has 90 days to evaluate a 100 MW+ request
Realistic energization, 50 MW2028 to 2029
VerificationTHIN (law and docket status verified; contract terms not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Salt Lake City?

PacifiCorp / Rocky Mountain Power: study fee not published; collateral not published; minimum bill not published; term not published.

When can a 50 MW load be energized in Salt Lake City?

2028 to 2029. Salt Lake City described as shorter time to power than Tier 1 markets (construction-owner market guide 2026); no JLL figure.

Which tariff applies to large loads in Salt Lake City?

Utah SB 132 (2025) large-load pathways; Large-Load Service Contract approved by Utah PSC; Oregon Schedule 401 pending under HB 3546; docket Utah PSC 26-035-05 (approved); OPUC UE 463 (pending); status: approved (Utah contract form); Oregon pending.

Is this rate proposed or approved?

Not yet final: approved (Utah contract form); Oregon pending. The table carries the filed terms and the docket to watch.

Sources

  1. Open Factory Large-Load Cost Table
  2. latitudemedia.com (2025-04-15)
  3. eta-publications.lbl.gov (Appendix 1)
  4. apps.puc.state.or.us (2026-05-07)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Salt Lake City: what a 50 MW connection costs under PacifiCorp / Rocky Mountain Power, August 21, 2026.