Phoenix (SRP): what a 50 MW connection costs under Salt River Project

What does a 50 MW connection cost in Phoenix (SRP)?

In short. In Phoenix (SRP), Salt River Project connects a 50 MW load under E-67 price plan (board-approved in the 2025 pricing process) and the Large Customer Integration Process (LCIP), docket SRP board pricing process 2025 (LBNL lists E-00000A-25-0069). Minimum bill: greater of actual use or 80% of forecasted demand (SRP may reduce if the customer pays for generation and infrastructure SRP would not otherwise build). Term: not published. Realistic energization: 2028 to 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketPhoenix (SRP), AZ (SRP (public power))
UtilitySalt River Project
Tariff or ruleE-67 price plan (board-approved in the 2025 pricing process) and the Large Customer Integration Process (LCIP)
DocketSRP board pricing process 2025 (LBNL lists E-00000A-25-0069)
Statusapproved
Large-load threshold20 MW of forecast load
Study feeLCIP study (fee not published)
Security or collateralcustomer pays LCIP-identified upgrades upfront
Minimum billgreater of actual use or 80% of forecasted demand (SRP may reduce if the customer pays for generation and infrastructure SRP would not otherwise build)
Contract termnot published
Rampnot published
Exit feenot published
CIAC exposurededicated transmission and substations paid by the customer; all LCIP upgrade costs paid upfront
Realistic energization, 50 MW2028 to 2029
VerificationPARTIAL (minimum bill and upfront payment verified via SRP commentary and LBNL; term and exit not public)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Phoenix (SRP)?

Salt River Project: study fee LCIP study (fee not published); collateral customer pays LCIP-identified upgrades upfront; minimum bill greater of actual use or 80% of forecasted demand (SRP may reduce if the customer pays for generation and infrastructure SRP would not otherwise build); term not published.

When can a 50 MW load be energized in Phoenix (SRP)?

2028 to 2029. JLL 2026 outlook: ~2.5 years average for a new 50 MW data center in Phoenix; data centers were 441 MW or 5.1% of SRP's 8, 542 MW 2025 peak; first LCIP cluster study of 25 applicants produced mixed results (CBRE H2 2025).

Which tariff applies to large loads in Phoenix (SRP)?

E-67 price plan (board-approved in the 2025 pricing process) and the Large Customer Integration Process (LCIP); docket SRP board pricing process 2025 (LBNL lists E-00000A-25-0069); status: approved.

Is this rate proposed or approved?

Approved or in effect as of the data date (approved). PARTIAL (minimum bill and upfront payment verified via SRP commentary and LBNL; term and exit not public).

Sources

  1. Open Factory Large-Load Cost Table
  2. azcapitoltimes.com (2026-03-31; SRP general manager commentary)
  3. eta-publications.lbl.gov p.5

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Phoenix (SRP): what a 50 MW connection costs under Salt River Project, August 21, 2026.