Phoenix (APS): what a 50 MW connection costs under Arizona Public Service

What does a 50 MW connection cost in Phoenix (APS)?

In short. In Phoenix (APS), Arizona Public Service connects a 50 MW load under Extra High Load Factor (XHLF) rate update with minimum bill and collateral; long-term contracts with upfront contributions, docket ACC E-01345A-25-0105 (June 2025 rate case; pending). Minimum bill (level not public). Term: long-term contracts (length not public). Realistic energization: 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketPhoenix (APS), AZ (APS (non-RTO))
UtilityArizona Public Service
Tariff or ruleExtra High Load Factor (XHLF) rate update with minimum bill and collateral; long-term contracts with upfront contributions
DocketACC E-01345A-25-0105 (June 2025 rate case; pending)
Statuspending
Large-load thresholdnot published (XHLF class)
Study feenot published
Security or collateralcollateral requirements (formula not public); upfront contributions to infrastructure under long-term contracts
Minimum billminimum bill (level not public)
Contract termlong-term contracts (length not public)
Rampnot published
Exit feenot published
CIAC exposurecustomer funds new infrastructure through upfront contributions under long-term contracts (APS statement)
Realistic energization, 50 MW2029
VerificationPARTIAL (utility statement and docket status verified; numbers not public)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Phoenix (APS)?

Arizona Public Service: study fee not published; collateral collateral requirements (formula not public); upfront contributions to infrastructure under long-term contracts; minimum bill minimum bill (level not public); term long-term contracts (length not public).

When can a 50 MW load be energized in Phoenix (APS)?

2029. JLL 2026 outlook: ~2.5 years average for a new 50 MW data center in Phoenix; APS had 4.5 GW committed and 19 GW in discussion (Aug 2025); Arizona task force flagged ~29 GW of proposed APS and SRP loads (Apr 2026).

Which tariff applies to large loads in Phoenix (APS)?

Extra High Load Factor (XHLF) rate update with minimum bill and collateral; long-term contracts with upfront contributions; docket ACC E-01345A-25-0105 (June 2025 rate case; pending); status: pending.

Is this rate proposed or approved?

Not yet final: pending. The table carries the filed terms and the docket to watch.

Sources

  1. Open Factory Large-Load Cost Table
  2. aps.com (accessed 2026-09-09)
  3. eta-publications.lbl.gov (Appendix 1)
  4. constructionowners.com (2026)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Phoenix (APS): what a 50 MW connection costs under Arizona Public Service, August 21, 2026.