ReferenceLarge-load power by market

Northern Virginia: what a 50 MW connection costs under Dominion Energy Virginia

What does a 50 MW connection cost in Northern Virginia?

In short. In Northern Virginia, Dominion Energy Virginia connects a 50 MW load under Schedule GS-5 (large-load class) plus SCC-ordered mandatory CIAC for direct-connect transmission, docket PUR-2025-00058 (GS-5 approved 2025-11-25). Minimum bill: 85% of contract demand for distribution and transmission; 60% for generation. Term: 14 years. Realistic energization: 2033. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketNorthern Virginia, VA (PJM)
UtilityDominion Energy Virginia
Tariff or ruleSchedule GS-5 (large-load class) plus SCC-ordered mandatory CIAC for direct-connect transmission
DocketPUR-2025-00058 (GS-5 approved 2025-11-25); PUR-2026-00056 (final order 2026-07-31)
StatusGS-5 approved; CIAC amendment to be filed within 90 days of 2026-07-31
Large-load threshold25 MW
Study feenot published in sources opened
Security or collateral$1.5 million per MW of contracted capacity
Minimum bill85% of contract demand for distribution and transmission; 60% for generation
Contract term14 years
Rampmax 4 years with minimum 20% of contract capacity per year
Exit feeexit fees in tariff (amount not in sources opened)
CIAC exposuremandatory CIAC for direct-connect substations and lines (net of expected transmission revenue) ordered 2026-07-31; higher-order transmission costs under review
Realistic energization, 50 MW2033
VerificationVERIFIED (SCC order; LBNL/Brattle brief) except study fee and exit-fee amount
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Northern Virginia?

Dominion Energy Virginia: study fee not published in sources opened; collateral $1.5 million per MW of contracted capacity; minimum bill 85% of contract demand for distribution and transmission; 60% for generation; term 14 years.

When can a 50 MW load be energized in Northern Virginia?

2033. JLL 2026 outlook: ~7 years average grid connection for a new 50 MW data center in N. Virginia; Dominion queue 70 GW vs 24.6 GW peak (Feb 2026).

Which tariff applies to large loads in Northern Virginia?

Schedule GS-5 (large-load class) plus SCC-ordered mandatory CIAC for direct-connect transmission; docket PUR-2025-00058 (GS-5 approved 2025-11-25); PUR-2026-00056 (final order 2026-07-31); status: GS-5 approved; CIAC amendment to be filed within 90 days of 2026-07-31.

Is this rate proposed or approved?

Approved or in effect as of the data date (GS-5 approved; CIAC amendment to be filed within 90 days of 2026-07-31). VERIFIED (SCC order; LBNL/Brattle brief) except study fee and exit-fee amount.

Sources

  1. Open Factory Large-Load Cost Table
  2. scc.virginia.gov (2026-07-31)
  3. eta-publications.lbl.gov (2026-08-10) pp.4-7 and 13
  4. jll.com (2026-03) p.18
  5. utilitydive.com (2026-02)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Northern Virginia: what a 50 MW connection costs under Dominion Energy Virginia, August 21, 2026.