ReferenceLarge-load power by market

Northern Indiana: what a 50 MW connection costs under Indiana Michigan Power

What does a 50 MW connection cost in Northern Indiana?

In short. In Northern Indiana, Indiana Michigan Power connects a 50 MW load under Industrial Power Tariff large-load amendments (settlement), docket IURC Cause 46097 (approved 2025-02-19). Minimum bill: not published for Indiana (I&M's proposed Michigan Large Power Tariff uses 90% of contract capacity). Term: at least 12 years after a ramp of up to 5 years. Realistic energization: 2028 to 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketNorthern Indiana, IN (PJM)
UtilityIndiana Michigan Power
Tariff or ruleIndustrial Power Tariff large-load amendments (settlement)
DocketIURC Cause 46097 (approved 2025-02-19)
Statusapproved
Large-load threshold70 MW per site or 150 MW aggregated across a company
Study feenot published
Security or collateralcollateral required (formula not in sources opened)
Minimum billnot published for Indiana (I&M's proposed Michigan Large Power Tariff uses 90% of contract capacity)
Contract termat least 12 years after a ramp of up to 5 years
Rampup to 5 years
Exit feeexit fee for termination or reductions above 20%; after year 5 a reduction of up to 20% with 42 months' notice is free; reductions above 20% need IURC approval
CIAC exposurenot published; costs to serve recovered from the large load per settlement (allocation deferred to a later case)
Realistic energization, 50 MW2028 to 2029
VerificationPARTIAL (threshold term ramp and exit verified via IURC order coverage; minimum demand and collateral not public)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Northern Indiana?

Indiana Michigan Power: study fee not published; collateral collateral required (formula not in sources opened); minimum bill not published for Indiana (I&M's proposed Michigan Large Power Tariff uses 90% of contract capacity); term at least 12 years after a ramp of up to 5 years.

When can a 50 MW load be energized in Northern Indiana?

2028 to 2029. Indiana territories described as less constrained than PJM markets to the east (construction-owner market guide 2026); I&M expects Indiana peak to rise from 2, 800 MW to more than 7, 000 MW by 2030.

Which tariff applies to large loads in Northern Indiana?

Industrial Power Tariff large-load amendments (settlement); docket IURC Cause 46097 (approved 2025-02-19); status: approved.

Is this rate proposed or approved?

Approved or in effect as of the data date (approved). PARTIAL (threshold term ramp and exit verified via IURC order coverage; minimum demand and collateral not public).

Sources

  1. Open Factory Large-Load Cost Table
  2. aep.com (2025-02-19)
  3. utilitydive.com (2024-11-25)
  4. utilitydive.com (2025-02-20)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Northern Indiana: what a 50 MW connection costs under Indiana Michigan Power, August 21, 2026.