ReferenceLarge-load power by market

Louisiana: what a 50 MW connection costs under Entergy Louisiana

What does a 50 MW connection cost in Louisiana?

In short. In Louisiana, Entergy Louisiana connects a 50 MW load under Large Load High Load Factor Power Service rate; customer-specific contracts for hyperscale loads (Meta), docket LPSC U-36959 (approved). Minimum charges in the Meta contract cover capital cost return fixed O&M taxes and insurance. Term: 5-year minimum contract under the tariff. Realistic energization: 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketLouisiana, LA (MISO)
UtilityEntergy Louisiana
Tariff or ruleLarge Load High Load Factor Power Service rate; customer-specific contracts for hyperscale loads (Meta)
DocketLPSC U-36959 (approved); Meta expansion filing April 2026
Statusapproved
Large-load thresholdnot published
Study feenot published
Security or collateralnot published
Minimum billminimum charges in the Meta contract cover capital cost return fixed O&M taxes and insurance; tariff minimum bill level not public
Contract term5-year minimum contract under the tariff; 20 years in the Meta contract
Rampnot published
Exit feenot published (Meta contract: Entergy may seek retained-generator status on early exit)
CIAC exposurecustomer pays for dedicated generation through minimum charges (Meta); tariff CIAC terms not opened
Realistic energization, 50 MW2029
VerificationTHIN (docket status and term verified via LBNL; rate sheet not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Louisiana?

Entergy Louisiana: study fee not published; collateral not published; minimum bill minimum charges in the Meta contract cover capital cost return fixed O&M taxes and insurance; tariff minimum bill level not public; term 5-year minimum contract under the tariff; 20 years in the Meta contract.

When can a 50 MW load be energized in Louisiana?

2029. Meta's contract takes effect in 2028; Entergy has a 7 to 12 GW pipeline after Meta; Entergy projects are one-third of MISO's fast-track interconnection process; no JLL figure.

Which tariff applies to large loads in Louisiana?

Large Load High Load Factor Power Service rate; customer-specific contracts for hyperscale loads (Meta); docket LPSC U-36959 (approved); Meta expansion filing April 2026; status: approved.

Is this rate proposed or approved?

Approved or in effect as of the data date (approved). THIN (docket status and term verified via LBNL; rate sheet not opened).

Sources

  1. Open Factory Large-Load Cost Table
  2. eta-publications.lbl.gov p.4 and Appendix 1
  3. blog.ucs.org (2026-08-10)
  4. utilitydive.com (2026-04)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Louisiana: what a 50 MW connection costs under Entergy Louisiana, August 21, 2026.