ReferenceLarge-load power by market

Dallas-Fort Worth: what a 50 MW connection costs under Oncor Electric Delivery

What does a 50 MW connection cost in Dallas-Fort Worth?

In short. In Dallas-Fort Worth, Oncor Electric Delivery connects a 50 MW load under SB 6 (75 MW+) and PUCT proposed 16 TAC 25.194; ERCOT Batch Zero (NPRR1325/PGRR145); standard TDSP facilities extension below 75 MW, docket PUCT Project 58481 (proposed rule published 2026-03-12; comments due 2026-04-17). Minimum bill: none (retail energy is bought from a REP; TDSP delivery charges follow 4CP demand). Term: none. Realistic energization: 2029. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketDallas-Fort Worth, TX (ERCOT)
UtilityOncor Electric Delivery
Tariff or ruleSB 6 (75 MW+) and PUCT proposed 16 TAC 25.194; ERCOT Batch Zero (NPRR1325/PGRR145); standard TDSP facilities extension below 75 MW
DocketPUCT Project 58481 (proposed rule published 2026-03-12; comments due 2026-04-17); Batch Zero approved by ERCOT board 2026-06-01 and PUCT 2026-06-18
Status25.194 still a proposal in sources opened; Batch Zero paused by the Governor's 2026-08-03 directive; ERCOT audit filing targeted 2026-12-10
Large-load threshold75 MW (SB 6 and Batch Zero); 25 MW for ERCOT's community-impact review
Study fee$100,000 for 75 to 250 MW and $300,000 above 250 MW plus actual study costs (proposed); below 75 MW: TDSP study (fee not published)
Security or collateral$50,000 per MW at the intermediate agreement (20% refundable on withdrawal) plus a non-refundable $50,000 per MW interconnection fee at the interconnection agreement (proposed); none of this applies below 75 MW
Minimum billnone (retail energy is bought from a REP; TDSP delivery charges follow 4CP demand)
Contract termnone
Rampnone required by rule
Exit fee80% of posted security forfeited on withdrawal (75 MW+ proposal)
CIAC exposure100% of direct interconnection costs including radial lines and substations with no revenue credit (75 MW+ proposal); standard tariff CIAC below 75 MW
Realistic energization, 50 MW2029
VerificationPARTIAL (regime verified from ERCOT/PUCT/Governor documents; Oncor's own tariff sheet not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Dallas-Fort Worth?

Oncor Electric Delivery: study fee $100,000 for 75 to 250 MW and $300,000 above 250 MW plus actual study costs (proposed); below 75 MW: TDSP study (fee not published); collateral $50,000 per MW at the intermediate agreement (20% refundable on withdrawal) plus a non-refundable $50,000 per MW interconnection fee at the interconnection agreement (proposed); none of this applies below 75 MW; minimum bill none (retail energy is bought from a REP; TDSP delivery charges follow 4CP demand); term none.

When can a 50 MW load be energized in Dallas-Fort Worth?

2029. JLL 2026 outlook: ~2.5 years average for a new 50 MW data center in Dallas before the pause; Batch Zero final transmission plan not expected before fall 2027; Oncor has 298 GW of requests and about 44 GW that met Batch Zero criteria.

Which tariff applies to large loads in Dallas-Fort Worth?

SB 6 (75 MW+) and PUCT proposed 16 TAC 25.194; ERCOT Batch Zero (NPRR1325/PGRR145); standard TDSP facilities extension below 75 MW; docket PUCT Project 58481 (proposed rule published 2026-03-12; comments due 2026-04-17); Batch Zero approved by ERCOT board 2026-06-01 and PUCT 2026-06-18; status: 25.194 still a proposal in sources opened; Batch Zero paused by the Governor's 2026-08-03 directive; ERCOT audit filing targeted 2026-12-10.

Is this rate proposed or approved?

Not yet final: 25.194 still a proposal in sources opened; Batch Zero paused by the Governor's 2026-08-03 directive; ERCOT audit filing targeted 2026-12-10. The table carries the filed terms and the docket to watch.

Sources

  1. Open Factory Large-Load Cost Table
  2. ercot.com (2026-06-18)
  3. ercot.com (2026-04-01)
  4. gtlaw.com (2026-03)
  5. gov.texas.gov (2026-08-03)
  6. utilitydive.com (2026-08-07)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Dallas-Fort Worth: what a 50 MW connection costs under Oncor Electric Delivery, August 21, 2026.