Colorado: what a 50 MW connection costs under Xcel Energy (Public Service Co. of Colorado)

What does a 50 MW connection cost in Colorado?

In short. In Colorado, Xcel Energy (Public Service Co. of Colorado) connects a 50 MW load under Large General Service - Transmission large-load tariff (proposed), docket CPUC 26AL-0137E (filed 2026-04-02; pending). Minimum bill: 80% of contracted power over the term plus a minimum monthly bill. Term: 15 years. Realistic energization: 2029 to 2030. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketColorado, CO (Xcel (non-RTO; SPP RTO West pending))
UtilityXcel Energy (Public Service Co. of Colorado)
Tariff or ruleLarge General Service - Transmission large-load tariff (proposed)
DocketCPUC 26AL-0137E (filed 2026-04-02; pending)
Statuspending
Large-load threshold50 MW
Study fee$120,000 deposit plus load and transmission studies; about $600,000 upfront
Security or collateralsecurity deposit equal to six months of operations
Minimum bill80% of contracted power over the term plus a minimum monthly bill
Contract term15 years
Rampnot published
Exit feesum of all remaining minimum monthly bills
CIAC exposurecustomer pays 100% of new generation it requires and the transmission to connect; prorated monthly fee for shared upgrades
Realistic energization, 50 MW2029 to 2030
VerificationPARTIAL (all seven cells reported by Colorado Sun from the filing; docket documents not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Colorado?

Xcel Energy (Public Service Co. of Colorado): study fee $120,000 deposit plus load and transmission studies; about $600,000 upfront; collateral security deposit equal to six months of operations; minimum bill 80% of contracted power over the term plus a minimum monthly bill; term 15 years.

When can a 50 MW load be energized in Colorado?

2029 to 2030. PSCo needs 950 MW of new generation for large loads within five years; CO PUC approved 6 GW of a 14 GW resource request; Xcel targets 6 GW more of data center contracts by end-2027; no JLL figure.

Which tariff applies to large loads in Colorado?

Large General Service - Transmission large-load tariff (proposed); docket CPUC 26AL-0137E (filed 2026-04-02; pending); status: pending.

Is this rate proposed or approved?

Not yet final: pending. The table carries the filed terms and the docket to watch.

Sources

  1. Open Factory Large-Load Cost Table
  2. coloradosun.com (2026-04-02)
  3. eta-publications.lbl.gov (Appendix 1)
  4. utilitydive.com (2026-05-06)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Colorado: what a 50 MW connection costs under Xcel Energy (Public Service Co. of Colorado), August 21, 2026.