ReferenceLarge-load power by market

Chicago: what a 50 MW connection costs under Commonwealth Edison

What does a 50 MW connection cost in Chicago?

In short. In Chicago, Commonwealth Edison connects a 50 MW load under Revised General Terms and Conditions for large loads plus FERC-approved Transmission Security Agreements (TSAs), docket ICC 25-0677 (approved). Minimum bill: committed revenue contributions with shortfall payments if usage misses commitments. Term: not published. Realistic energization: 2031. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketChicago, IL (PJM)
UtilityCommonwealth Edison
Tariff or ruleRevised General Terms and Conditions for large loads plus FERC-approved Transmission Security Agreements (TSAs)
DocketICC 25-0677 (approved); FERC TSA orders Feb to Mar 2026
Statusapproved
Large-load thresholdnot published (TSAs are for transmission-level loads)
Study feenot published
Security or collateralcredit obligations under TSAs; 4 GW of signed TSAs have posted about $1 billion
Minimum billcommitted revenue contributions with shortfall payments if usage misses commitments
Contract termnot published
Rampdefined ramp in each TSA
Exit feetermination-fee schedule in each TSA
CIAC exposuretransmission facilities secured by the TSA credit obligations; customer facility readiness obligation
Realistic energization, 50 MW2031
VerificationPARTIAL (TSA structure verified via FERC orders as reported; ICC terms not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Chicago?

Commonwealth Edison: study fee not published; collateral credit obligations under TSAs; 4 GW of signed TSAs have posted about $1 billion; minimum bill committed revenue contributions with shortfall payments if usage misses commitments; term not published.

When can a 50 MW load be energized in Chicago?

2031. JLL 2026 outlook: ~5 years average for a new 50 MW data center in Chicago; ComEd has ~9 GW of high-probability data center load; Exelon's pipeline fell from 43 GW to 25 GW in Q2 2026.

Which tariff applies to large loads in Chicago?

Revised General Terms and Conditions for large loads plus FERC-approved Transmission Security Agreements (TSAs); docket ICC 25-0677 (approved); FERC TSA orders Feb to Mar 2026; status: approved.

Is this rate proposed or approved?

Approved or in effect as of the data date (approved). PARTIAL (TSA structure verified via FERC orders as reported; ICC terms not opened).

Sources

  1. Open Factory Large-Load Cost Table
  2. utilitydive.com (2026-03-11)
  3. utilitydive.com (2026-07-31)
  4. eta-publications.lbl.gov (Appendix 1)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Chicago: what a 50 MW connection costs under Commonwealth Edison, August 21, 2026.