ReferenceLarge-load power by market

Carolinas: what a 50 MW connection costs under Duke Energy Carolinas

What does a 50 MW connection cost in Carolinas?

In short. In Carolinas, Duke Energy Carolinas connects a 50 MW load under Schedule HLF (High Load Factor) large-load provisions proposed in the 2026 rate case; existing contracts with minimum demand and credit support, docket NCUC E-7 Sub 1329 (filed late June 2026; pending). Minimum bill: 75% of contracted demand. Term: 10 or 15 years depending on load size. Realistic energization: 2029 to 2030. Open Factory's Large-Load Cost Table, as of August 21, 2026.

Facts

MarketCarolinas, NC/SC (Duke (non-RTO))
UtilityDuke Energy Carolinas
Tariff or ruleSchedule HLF (High Load Factor) large-load provisions proposed in the 2026 rate case; existing contracts with minimum demand and credit support
DocketNCUC E-7 Sub 1329 (filed late June 2026; pending)
Statuspending; tariff would start in 2027
Large-load threshold50 MW at 80% load factor or 100 MW at any load factor
Study feenot published in sources opened
Security or collateralsecurity (cash or letter of credit) covering the minimum bills; existing contracts use credit support and refundable capital advances
Minimum bill75% of contracted demand
Contract term10 or 15 years depending on load size
Rampnot published
Exit fee25% of remaining bills
CIAC exposurerefundable capital advances in existing contracts; Public Staff asked that ~$200M of $247M of proposed grid upgrades be assigned to large loads
Realistic energization, 50 MW2029 to 2030
VerificationPARTIAL (terms from Latitude Media reporting on the filing; docket documents not opened)
Data as ofAugust 21, 2026

Questions

What does a 50 MW connection cost in Carolinas?

Duke Energy Carolinas: study fee not published in sources opened; collateral security (cash or letter of credit) covering the minimum bills; existing contracts use credit support and refundable capital advances; minimum bill 75% of contracted demand; term 10 or 15 years depending on load size.

When can a 50 MW load be energized in Carolinas?

2029 to 2030. Duke has 7.6 GW of executed data center agreements (two-thirds under construction) and 7.8 GW late-stage; 14 GW of new generation by 2031; no market-level JLL figure.

Which tariff applies to large loads in Carolinas?

Schedule HLF (High Load Factor) large-load provisions proposed in the 2026 rate case; existing contracts with minimum demand and credit support; docket NCUC E-7 Sub 1329 (filed late June 2026; pending); status: pending; tariff would start in 2027.

Is this rate proposed or approved?

Not yet final: pending; tariff would start in 2027. The table carries the filed terms and the docket to watch.

Sources

  1. Open Factory Large-Load Cost Table
  2. latitudemedia.com (2026-07-08)
  3. utilitydive.com (2026-05)
  4. eta-publications.lbl.gov (Appendix 1)

Data as of August 21, 2026. This page is rebuilt from the same table the Large-Load Interconnection Cost, the API and the MCP server read, so the figures cannot differ. Also available as plain markdown. Cite as Open Factory, Carolinas: what a 50 MW connection costs under Duke Energy Carolinas, August 21, 2026.