# Power panelboard, I-Line assembled lead time: 14 to 19 weeks

URL: https://open-factory.com/lead-times/power-panelboard/
Data as of: 2026-09-02
Publisher: Open Factory, https://open-factory.com

**Power panelboard, I-Line assembled: how long is the lead time?** Power panelboard, I-Line assembled is quoted at 14 to 19 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 4 product rows, made-to-order weeks from release to manufacturing. Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

## Facts

- Equipment class: Power panelboard, I-Line assembled (Schneider)
- Group: Schneider Electric Lead Times Guide
- Published lead time: 14 to 19 weeks
- Basis: 4 product rows, made-to-order weeks from release to manufacturing
- Published by: Schneider Electric Lead Times Guide, September 2026 edition (https://www.se.com/us/en/download/document/Monthly_Lead/)
- Document date: September 2, 2026
- Data as of: September 2, 2026

## Questions

### Power panelboard, I-Line assembled: how long is the lead time?

14 to 19 weeks, per Schneider Electric Lead Times Guide, September 2026 edition. 4 product rows, made-to-order weeks from release to manufacturing.

### Who published this lead time?

Schneider Electric Lead Times Guide, September 2026 edition. This is the OEM's own planning figure for made-to-order product, not a quote. Open Factory reprints it with the document and its date.

### How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

## Related articles

- [Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line](https://open-factory.com/articles/skids-vs-stick-built/)
- [The 2 MW Plant Service Upgrade Nobody Budgets Right](https://open-factory.com/articles/2mw-plant-service-upgrade/)
- [What 50 MW Costs in 15 US Markets](https://open-factory.com/articles/what-50mw-costs-15-markets/)
- [Reading a Switchgear Quote: The Eleven Line Items That Hide the Schedule](https://open-factory.com/articles/switchgear-quote-anatomy/)
- [The $306k Machine: A Record Half-Year With Fewer Units](https://open-factory.com/articles/machine-tool-record-fewer-units/)
- [Grainger vs McMaster vs Amazon Business: A 50-SKU Price Basket](https://open-factory.com/articles/mro-price-basket/)

## Sources

- [Open Factory Lead-Time Monitor](https://open-factory.com/models/lead-time-monitor/)
- [Schneider Electric Lead Times Guide, September 2026 edition](https://www.se.com/us/en/download/document/Monthly_Lead/)

Model: https://open-factory.com/models/lead-time-monitor/
Calculator: https://open-factory.com/tools/lead-time-schedule/