# Genset High-horsepower data center gensets lead time: 78 to 104 weeks

URL: https://open-factory.com/lead-times/genset-high-horsepower-data-center-gensets-qsk95-class/
Data as of: 2026-09-02
Publisher: Open Factory, https://open-factory.com

**Genset High-horsepower data center gensets: how long is the lead time?** Genset High-horsepower data center gensets is quoted at 78 to 104 weeks, per Cummins 10-K FY2025 (February 10, 2026). Cummins 10-K FY2025 (strong demand for our data center products extending out six to eight quarters). Open Factory's Lead-Time Monitor carries this figure as of September 2, 2026.

## Facts

- Equipment class: Genset High-horsepower data center gensets (QSK95 class) (Cummins)
- Group: Gensets and transfer switches (published by contractors and OEMs)
- Published lead time: 78 to 104 weeks
- Basis: Cummins 10-K FY2025 (strong demand for our data center products extending out six to eight quarters)
- Published by: Cummins 10-K FY2025 (https://www.sec.gov/Archives/edgar/data/26172/000002617226000009/cmi-20251231.htm)
- Document date: February 10, 2026
- Data as of: September 2, 2026

## Questions

### Genset High-horsepower data center gensets: how long is the lead time?

78 to 104 weeks, per Cummins 10-K FY2025, dated February 10, 2026. Cummins 10-K FY2025 (strong demand for our data center products extending out six to eight quarters).

### Who published this lead time?

Cummins 10-K FY2025. This is the publisher's own figure, labelled as theirs. Open Factory reprints it with the document and its date.

### How often is this page updated?

Monthly, when the Lead-Time Monitor edition is released. The date on the page is the date of the data, not of the page.

## Related articles

- [Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin](https://open-factory.com/articles/liquidated-damages/)
- [How to Write an RFQ for Capital Equipment in 2026](https://open-factory.com/articles/rfq-capital-equipment/)
- [The Used and Refurbished Market Nobody Indexes](https://open-factory.com/articles/used-refurbished-market/)
- [Tariff Bill of Materials: What Sections 232 and 301 Add to a UPS, a Lineup, a Genset and a Megapack](https://open-factory.com/articles/tariff-bom-electrical/)
- [Introducing the Public Bid-Tab Price Book](https://open-factory.com/articles/bid-tab-price-book-launch/)
- [Cummins and Caterpillar Are Sold Out Through 2028](https://open-factory.com/articles/gensets-sold-out-2028/)

## Sources

- [Open Factory Lead-Time Monitor](https://open-factory.com/models/lead-time-monitor/)
- [Cummins 10-K FY2025](https://www.sec.gov/Archives/edgar/data/26172/000002617226000009/cmi-20251231.htm)

Model: https://open-factory.com/models/lead-time-monitor/
Calculator: https://open-factory.com/tools/lead-time-schedule/